IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

5,520

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0580 # 04 Y:1999 04 1999 REUSE / RECYCLE/ SELL PAPER PRODUCTS $840 $0 Implemented
OK0580 # 05 Y:1999 05 1999 TURN OFF EQUIPMENT WHEN NOT IN USE $611 $0 Implemented
ME0280 # 09 Y:1999 09 1999 MODIFY CURRENT INCENTIVE PROGRAM $55,341 $30,500 Implemented
ME0280 # 08 Y:1999 08 1999 INTERLOCK HEATING AND AIR CONDITIONING SYSTEMS TO PREVENT SIMULTANEOUS OPERATION $1,092 $1,240 Implemented
ME0280 # 07 Y:1999 07 1999 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,619 $1,000 Not Implemented
ME0280 # 06 Y:1999 06 1999 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $3,402 $4,940 Implemented
ME0280 # 05 Y:1999 05 1999 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $9,204 $1,000 Not Implemented
ME0280 # 04 Y:1999 04 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $10,958 $28,528 Implemented
ME0280 # 03 Y:1999 03 1999 MODIFY CURRENT INCENTIVE PROGRAM $15,000 $0 Implemented
ME0280 # 02 Y:1999 02 1999 MOVE PRODUCT USING MECHANICAL MEANS $105,600 $6,000 Implemented
ME0280 # 01 Y:1999 01 1999 INSTALL SENSORS TO DETECT DEFECTS $243,000 $20,108 Implemented
AR0177 # 01 Y:1999 01 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,480 $1,214 Not Implemented
AR0177 # 02 Y:1999 02 1999 INSTALL / REPAIR INSULATION ON STEAM LINES $5,452 $6,656 Not Implemented
AR0177 # 03 Y:1999 03 1999 USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS $48,768 $92,500 Not Implemented
AR0177 # 04 Y:1999 04 1999 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER $5,480 $8,000 Not Implemented
AR0177 # 05 Y:1999 05 1999 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS $384,000 $400,000 Not Implemented
UF0238 # 01 Y:1999 01 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,479 $7,893 Not Implemented
UF0238 # 02 Y:1999 02 1999 USE OPTIMUM THICKNESS INSULATION $1,894 $1,361 Implemented
UF0238 # 03 Y:1999 03 1999 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $1,287 $0 Implemented
UF0238 # 04 Y:1999 04 1999 ENHANCE SENSITIVITY OF TEMPERATURE CONTROL AND CUTOFF $584 $20 Implemented
UF0238 # 05 Y:1999 05 1999 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,670 $0 Implemented
UF0238 # 06 Y:1999 06 1999 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $6,767 $1,605 Implemented
UF0238 # 07 Y:1999 07 1999 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $1,699 $2,720 Implemented
ME0279 # 09 Y:1999 09 1999 MINIMIZE WATER USAGE $751 $1,345 Implemented
ME0279 # 08 Y:1999 08 1999 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER $9,525 $10,000 Not Implemented