Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,515
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OD0125 # 04 Y:1998 | 04 | 1998 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $5,182 | $8,000 | Not Implemented |
OD0125 # 05 Y:1998 | 05 | 1998 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $4,293 | $1,295 | Not Implemented |
OD0125 # 06 Y:1998 | 06 | 1998 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $619 | $0 | Implemented |
OD0124 # 01 Y:1998 | 01 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,935 | $6,012 | Implemented |
OD0124 # 02 Y:1998 | 02 | 1998 | INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS | $437 | $1,290 | Not Implemented |
OD0124 # 03 Y:1998 | 03 | 1998 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,225 | $5,625 | Not Implemented |
OD0124 # 04 Y:1998 | 04 | 1998 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $7,805 | $4,595 | Not Implemented |
NC0153 # 01 Y:1998 | 01 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $541 | $800 | Not Implemented |
NC0153 # 02 Y:1998 | 02 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,691 | $18,850 | Not Implemented |
NC0153 # 03 Y:1998 | 03 | 1998 | ADD AREA LIGHTING SWITCHES | $91 | $300 | Not Implemented |
NC0153 # 04 Y:1998 | 04 | 1998 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $3,508 | $500 | Not Implemented |
NC0153 # 05 Y:1998 | 05 | 1998 | INSTALL SKYLIGHTS | $10,344 | $36,000 | Not Implemented |
NC0153 # 06 Y:1998 | 06 | 1998 | UTILIZE OUTSIDE AIR INSTEAD OF CONDITIONED AIR FOR DRYING | $3,423 | $3,000 | Not Implemented |
NC0153 # 07 Y:1998 | 07 | 1998 | CLEAR AND RENT EXISTING SPACE | $28,000 | $20,500 | Not Implemented |
TN0645 # 01 Y:1998 | 01 | 1998 | ALLOW DRAINAGE BEFORE WITHDRAWING OBJECT | $408,630 | $24,685 | Implemented |
TN0645 # 02 Y:1998 | 02 | 1998 | RECOVERY METALS FROM RINSE WATER(EVAP., ION EXCHANGE, RO, ELECTROLYSIS, ELECTRODIALYSIS) AND REUSE RINSE WATER | $277,345 | $644,800 | Not Implemented |
TN0645 # 03 Y:1998 | 03 | 1998 | REDUCE SOLUTION DRAG-OUT TO PREVENT SOLUTION LOSS | $237,600 | $153,485 | Not Implemented |
TN0645 # 04 Y:1998 | 04 | 1998 | SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE | $221,455 | $70,000 | Not Implemented |
TN0645 # 05 Y:1998 | 05 | 1998 | INITIATE A PROGRAM TO ACQUIRE ISO CERTIFICATION | $198,225 | $250,000 | Not Implemented |
TN0645 # 06 Y:1998 | 06 | 1998 | USE A DIFFERENT OR RECYCLED RAW MATERIAL | $51,945 | $200,000 | Not Implemented |
TN0645 # 07 Y:1998 | 07 | 1998 | USE DEIONIZED WATER IN UPSTREAM RINSE TANKS | $48,650 | $120,000 | Not Implemented |
TN0645 # 08 Y:1998 | 08 | 1998 | TREAT AND REUSE RINSE WATERS | $28,105 | $69,200 | Not Implemented |
TN0645 # 09 Y:1998 | 09 | 1998 | INSTALL SET-BACK TIMERS | $15,755 | $1,555 | Not Implemented |
TN0645 # 10 Y:1998 | 10 | 1998 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $9,390 | $8,000 | Implemented |
TN0645 # 11 Y:1998 | 11 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,880 | $5,000 | Implemented |