IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

161,963

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD0066 # 01 Y:1982 01 1982 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $9,419 $2,525 Implemented
UD0066 # 02 Y:1982 02 1982 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED $147 $0 Implemented
UD0066 # 03 Y:1982 03 1982 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $769 $0 Implemented
UD0068 # 01 Y:1982 01 1982 CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS $21,549 $19,000 Not Implemented
UD0068 # 02 Y:1982 02 1982 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $931 $406 Not Implemented
UD0068 # 03 Y:1982 03 1982 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED $99 $0 Not Implemented
UD0069 # 01 Y:1982 01 1982 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,154 $272 Not Implemented
UD0069 # 02 Y:1982 02 1982 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $257 $500 Not Implemented
UD0069 # 03 Y:1982 03 1982 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $1,195 $3,000 Not Implemented
UD0069 # 04 Y:1982 04 1982 REPLACE BROKEN WINDOWS AND/OR WINDOW SASH $2,157 $2,629 Not Implemented
UD0070 # 01 Y:1982 01 1982 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $594 $158 Not Implemented
UD0070 # 02 Y:1982 02 1982 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT $6,051 $10,000 Implemented
UD0070 # 03 Y:1982 03 1982 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS $13,079 $15,000 Implemented
UD0070 # 04 Y:1982 04 1982 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $34,531 $43,000 Not Implemented
OK0064 # 01 Y:1982 01 1982 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $707 $56 Implemented
OK0064 # 02 Y:1982 02 1982 INSTALL TIMERS AND/OR THERMOSTATS $1,830 $400 Implemented
OK0064 # 03 Y:1982 03 1982 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,330 $1,405 Implemented
OK0064 # 04 Y:1982 04 1982 INSTALL TIMERS AND/OR THERMOSTATS $1,749 $560 Implemented
OK0064 # 05 Y:1982 05 1982 INSTALL TIMERS AND/OR THERMOSTATS $485 $0 Implemented
OK0064 # 06 Y:1982 06 1982 DE-ENERGIZE EXCESS TRANSFORMER CAPACITY $586 $0 Implemented
OK0066 # 01 Y:1982 01 1982 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $2,410 $9,010 Not Implemented
OK0066 # 02 Y:1982 02 1982 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $973 $633 Implemented
OK0066 # 03 Y:1982 03 1982 USE DEMAND CONTROLLER OR LOAD SHEDDER $718 $433 Not Implemented
OK0066 # 04 Y:1982 04 1982 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $1,042 $0 Not Implemented
OK0066 # 05 Y:1982 05 1982 OPTIMIZE PLANT POWER FACTOR $1,504 $1,520 Not Implemented