Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,715
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0566 # 08 Y:2016 | 08 | 2016 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,802 | $12,000 | Not Implemented |
NC0566 # 09 Y:2016 | 09 | 2016 | REPAIR AND ELIMINATE STEAM LEAKS | $2,230 | $1,000 | Implemented |
NC0566 # 10 Y:2016 | 10 | 2016 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,287 | $2,000 | Implemented |
NC0566 # 11 Y:2016 | 11 | 2016 | DEVELOP A REPAIR/REPLACE POLICY | $4,453 | $4,256 | Implemented |
NC0566 # 12 Y:2016 | 12 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,706 | $230 | Implemented |
IA0557 # 01 Y:2016 | 01 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $44,271 | $95,210 | Not Implemented |
IA0557 # 02 Y:2016 | 02 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,548 | $500 | Not Implemented |
IA0557 # 03 Y:2016 | 03 | 2016 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,367 | $29,084 | Not Implemented |
IA0557 # 04 Y:2016 | 04 | 2016 | OPTIMIZE PLANT POWER FACTOR | $4,037 | $4,835 | Not Implemented |
IA0557 # 05 Y:2016 | 05 | 2016 | INSTALL OCCUPANCY SENSORS | $3,284 | $5,488 | Not Implemented |
IA0557 # 06 Y:2016 | 06 | 2016 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,719 | $5,030 | Implemented |
IA0557 # 07 Y:2016 | 07 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,648 | $189 | Implemented |
IA0557 # 08 Y:2016 | 08 | 2016 | INSULATE BARE EQUIPMENT | $553 | $242 | Implemented |
IA0557 # 09 Y:2016 | 09 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $461 | $35 | Implemented |
IA0557 # 10 Y:2016 | 10 | 2016 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $420 | $398 | Not Implemented |
OR0672 # 01 Y:2016 | 01 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $30,924 | $26,614 | Not Implemented |
OR0672 # 02 Y:2016 | 02 | 2016 | INCREASE AMOUNT OF CONDENSATE RETURNED | $21,014 | $35,396 | Not Implemented |
OR0672 # 03 Y:2016 | 03 | 2016 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $39,775 | $138,248 | Not Implemented |
UD0951 # 01 Y:2016 | 01 | 2016 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $4,773 | $0 | Not Implemented |
UD0951 # 02 Y:2016 | 02 | 2016 | INSTALL OCCUPANCY SENSORS | $3,278 | $1,200 | Not Implemented |
UD0951 # 03 Y:2016 | 03 | 2016 | CONVERT TO AIR ASSISTED / AIRLESS PAINT GUNS | $5,257 | $700 | Not Implemented |
UD0951 # 04 Y:2016 | 04 | 2016 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $780 | $750 | Not Implemented |
UD0951 # 05 Y:2016 | 05 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $746 | $50 | Not Implemented |
UD0951 # 06 Y:2016 | 06 | 2016 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $3,332 | $3,750 | Implemented |
SF0487 # 01 Y:2016 | 01 | 2016 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $5,356 | $0 | Implemented |