Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,738
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AR0039 # 08 Y:1994 | 08 | 1994 | REPLACE ELECTRIC MOTOR WITH FOSSIL FUEL ENGINE | $26,724 | $32,000 | Not Implemented |
AR0038 # 01 Y:1994 | 01 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,079 | $300 | Implemented |
AR0038 # 02 Y:1994 | 02 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,118 | $200 | Implemented |
AR0038 # 03 Y:1994 | 03 | 1994 | USE DIRECT AIR SUPPLY TO EXHAUST HOODS | $4,094 | $2,000 | Implemented |
AR0038 # 04 Y:1994 | 04 | 1994 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $4,584 | $220 | Implemented |
AR0038 # 05 Y:1994 | 05 | 1994 | REPLACE ELECTRIC MOTOR WITH FOSSIL FUEL ENGINE | $20,991 | $30,000 | Not Implemented |
AR0037 # 01 Y:1994 | 01 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $7,587 | $2,180 | Implemented |
AR0037 # 02 Y:1994 | 02 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,890 | $3,320 | Implemented |
AR0037 # 03 Y:1994 | 03 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,520 | $767 | Implemented |
AR0037 # 04 Y:1994 | 04 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,105 | $50 | Implemented |
AR0037 # 05 Y:1994 | 05 | 1994 | REPLACE ELECTRIC MOTORS WITH BACK PRESSURE STEAM TURBINES AND USE EXHAUST STEAM FOR PROCESS HEAT | $30,719 | $5,500 | Implemented |
AR0036 # 01 Y:1994 | 01 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,190 | $250 | Implemented |
AR0036 # 02 Y:1994 | 02 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,029 | $6,297 | Implemented |
AR0036 # 03 Y:1994 | 03 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,478 | $7,250 | Implemented |
AR0036 # 04 Y:1994 | 04 | 1994 | RECOVER WASTE HEAT FROM EQUIPMENT | $580 | $400 | Implemented |
AR0036 # 05 Y:1994 | 05 | 1994 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $843 | $508 | Implemented |
AR0033 # 01 Y:1994 | 01 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,144 | $750 | Implemented |
AR0033 # 02 Y:1994 | 02 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,939 | $8,697 | Implemented |
AR0033 # 03 Y:1994 | 03 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $847 | $753 | Implemented |
AR0033 # 04 Y:1994 | 04 | 1994 | REPLACE ELECTRIC MOTOR WITH FOSSIL FUEL ENGINE | $-5,000 | $30,000 | Not Implemented |
AR0033 # 05 Y:1994 | 05 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,903 | $4,477 | Implemented |
AR0033 # 06 Y:1994 | 06 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,412 | $550 | Implemented |
AR0033 # 07 Y:1994 | 07 | 1994 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,255 | $500 | Implemented |
AR0033 # 08 Y:1994 | 08 | 1994 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,729 | $100 | Implemented |
AR0032 # 01 Y:1994 | 01 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,550 | $1,058 | Implemented |