IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

334

matching recommendations
Reset
SIC 20 Food and Kindred Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD1012 # 05 Y:2020 05 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $14,521 $1,000 Not Implemented
UD1012 # 06 Y:2020 06 2020 USE EXCESS COLD PROCESS FLUID FOR INDUSTRIAL COOLING NEEDS $67,773 $0 Implemented
UD1012 # 07 Y:2020 07 2020 UTILIZE AN EVAPORATIVE AIR PRE-COOLER OR OTHER HEAT EXCHANGER IN AC SYSTEM $49,540 $21,295 Implemented
UD1012 # 08 Y:2020 08 2020 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $46,434 $0 Not Implemented
UD1012 # 09 Y:2020 09 2020 UTILIZE A LESS EXPENSIVE COOLING METHOD $27,338 $0 Implemented
UD1012 # 10 Y:2020 10 2020 OPTIMIZE PLANT POWER FACTOR $145,150 $100,000 Not Implemented
UD1012 # 11 Y:2020 11 2020 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $86,219 $9,464 Not Implemented
UD1012 # 17 Y:2020 17 2020 USE DIRECT AIR SUPPLY TO EXHAUST HOODS $24,810 $35,000 Implemented
IC0231 # 01 Y:2020 01 2020 OPTIMIZE PLANT POWER FACTOR $15,040 $26,145 Implemented
IC0231 # 05 Y:2020 05 2020 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $5,416 $0 Implemented
IC0231 # 04 Y:2020 04 2020 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $12,061 $2,400 Not Implemented
IC0231 # 02 Y:2020 02 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $21,285 $6,673 Implemented
IC0231 # 03 Y:2020 03 2020 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $5,211 $50,440 Implemented
IP0130 # 05 Y:2020 05 2020 INSTALL OCCUPANCY SENSORS $539 $348 Not Implemented
IP0130 # 07 Y:2020 07 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $967 $1,966 Implemented
IP0130 # 06 Y:2020 06 2020 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $537 $396 Implemented
IP0130 # 04 Y:2020 04 2020 OPTIMIZE PLANT POWER FACTOR $41,119 $18,096 Not Implemented
IP0130 # 03 Y:2020 03 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $5,236 $208 Implemented
IP0130 # 01 Y:2020 01 2020 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $547 $0 Not Implemented
IP0130 # 02 Y:2020 02 2020 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $6,064 $70 Implemented
IP0125 # 03 Y:2019 03 2019 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $932 $315 Implemented
IP0125 # 01 Y:2019 01 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,774 $150 Not Implemented
IP0125 # 02 Y:2019 02 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,180 $354 Implemented
IP0125 # 04 Y:2019 04 2019 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $908 $1,344 Implemented
IP0125 # 07 Y:2019 07 2019 REDUCE EXCESSIVE BOILER BLOWDOWN $2,364 $6,720 Implemented