Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,587
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0739 # 01 Y:2015 | 01 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,369 | $11,834 | Not Implemented |
MA0739 # 04 Y:2015 | 04 | 2015 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $880 | $1,285 | Implemented |
MA0739 # 07 Y:2015 | 07 | 2015 | PAY UTILITY BILLS ON TIME | $426 | $500 | Implemented |
MA0739 # 03 Y:2015 | 03 | 2015 | INSTALL / REPAIR INSULATION ON STEAM LINES | $927 | $1,570 | Implemented |
MA0739 # 02 Y:2015 | 02 | 2015 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,543 | $500 | Implemented |
MA0739 # 05 Y:2015 | 05 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $864 | $2,635 | Not Implemented |
MA0739 # 06 Y:2015 | 06 | 2015 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $475 | $915 | Not Implemented |
MA0723 # 03 Y:2014 | 03 | 2014 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $16,628 | $5,000 | Implemented |
MA0723 # 05 Y:2014 | 05 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,158 | $1,250 | Implemented |
MA0723 # 02 Y:2014 | 02 | 2014 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $20,745 | $110,500 | Implemented |
MA0723 # 04 Y:2014 | 04 | 2014 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $11,047 | $32,000 | Not Implemented |
MA0723 # 01 Y:2014 | 01 | 2014 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $23,304 | $90,000 | Implemented |
MA0607 # 06 Y:2006 | 06 | 2006 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $10,577 | $1,870 | Not Implemented |
MA0607 # 05 Y:2006 | 05 | 2006 | USE UTILITY CONTROLLED POWER MANAGEMENT | $12,223 | $14,000 | Not Implemented |
MA0607 # 07 Y:2006 | 07 | 2006 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $6,860 | $3,500 | Not Implemented |
MA0607 # 01 Y:2006 | 01 | 2006 | BURN FOSSIL FUEL TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR AND USE STEAM EXHAUST FOR HEAT | $46,963 | $0 | Not Implemented |
MA0607 # 03 Y:2006 | 03 | 2006 | BURN A LESS EXPENSIVE GRADE OF FUEL | $14,261 | $5,500 | Not Implemented |
MA0607 # 02 Y:2006 | 02 | 2006 | REDUCE VENTILATION AIR | $45,943 | $10,400 | Not Implemented |
MA0607 # 04 Y:2006 | 04 | 2006 | REDUCE VENTILATION AIR | $12,889 | $1,700 | Not Implemented |
MA0565 # 03 Y:2004 | 03 | 2004 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $5,088 | $8,000 | Not Implemented |
MA0565 # 05 Y:2004 | 05 | 2004 | INSULATE BARE EQUIPMENT | $2,705 | $754 | Implemented |
MA0565 # 04 Y:2004 | 04 | 2004 | REPLACE BOILER | $2,760 | $750 | Implemented |
MA0565 # 07 Y:2004 | 07 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $656 | $548 | Not Implemented |
MA0565 # 06 Y:2004 | 06 | 2004 | INSULATE FEEDWATER TANK | $873 | $300 | Implemented |
MA0565 # 01 Y:2004 | 01 | 2004 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $216,000 | $125,000 | Implemented |