IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

139

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UM0237 # 02 Y:2003 02 2003 ISOLATE HOT OR COLD EQUIPMENT $11,459 $10,000 Implemented
UM0237 # 03 Y:2003 03 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,000 $2,498 Not Implemented
UM0237 # 04 Y:2003 04 2003 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $3,937 $1,650 Implemented
UM0237 # 05 Y:2003 05 2003 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $4,146 $2,100 Not Implemented
UM0236 # 01 Y:2003 01 2003 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $9,379 $700 Not Implemented
UM0236 # 02 Y:2003 02 2003 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $8,424 $2,000 Not Implemented
UM0236 # 03 Y:2003 03 2003 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $7,861 $2,500 Implemented
UM0236 # 04 Y:2003 04 2003 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,209 $500 Not Implemented
UM0236 # 05 Y:2003 05 2003 INSULATE BARE EQUIPMENT $1,777 $2,400 Not Implemented
UM0236 # 06 Y:2003 06 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $680 $5,018 Not Implemented
UM0235 # 01 Y:2003 01 2003 REDUCE SCRAP PRODUCTION $109,333 $9,600 Not Implemented
UM0235 # 02 Y:2003 02 2003 $96,000 $300,000 Not Implemented
UM0235 # 03 Y:2003 03 2003 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $7,576 $9,600 Implemented
UM0235 # 04 Y:2003 04 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,470 $9,227 Not Implemented
UM0235 # 05 Y:2003 05 2003 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,415 $675 Implemented
UM0234 # 01 Y:2003 01 2003 RECOVER WASTE HEAT FROM EQUIPMENT $71,900 $180,000 Implemented
UM0234 # 02 Y:2003 02 2003 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $27,488 $360 Not Implemented
UM0234 # 03 Y:2003 03 2003 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,415 $2,925 Not Implemented
UM0234 # 04 Y:2003 04 2003 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $10,603 $120,000 Implemented
UM0234 # 05 Y:2003 05 2003 COVER OPEN TANKS $8,523 $2,000 Not Implemented
UM0234 # 06 Y:2003 06 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,198 $5,219 Not Implemented
UM0233 # 01 Y:2003 01 2003 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER $41,800 $32,000 Not Implemented
UM0233 # 02 Y:2003 02 2003 RECOVER WASTE HEAT FROM EQUIPMENT $2,064 $500 Implemented
UM0233 # 03 Y:2003 03 2003 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,745 $150 Implemented
UM0233 # 04 Y:2003 04 2003 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,037 $50 Implemented