ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0316 # 04 Y:2006 | 04 | 2006 | INSTALL OCCUPANCY SENSORS | $1,033 | $675 | Implemented |
BD0316 # 05 Y:2006 | 05 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $679 | $2,102 | Implemented |
BD0316 # 03 Y:2006 | 03 | 2006 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $13,153 | $8,363 | Implemented |
BD0316 # 02 Y:2006 | 02 | 2006 | COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER | $4,724 | $1,200 | Implemented |
BD0316 # 01 Y:2006 | 01 | 2006 | USE SYNTHETIC LUBRICANT | $7,871 | $800 | Not Implemented |
IA0389 # 01 Y:2006 | 01 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $394 | $344 | Not Implemented |
IA0389 # 09 Y:2006 | 09 | 2006 | UPGRADE OBSOLETE EQUIPMENT | $17,486 | $87,000 | Not Implemented |
IA0389 # 05 Y:2006 | 05 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $848 | $1,836 | Not Implemented |
IA0389 # 06 Y:2006 | 06 | 2006 | INSTALL OCCUPANCY SENSORS | $667 | $77 | Not Implemented |
IA0389 # 07 Y:2006 | 07 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $493 | $305 | Not Implemented |
IA0389 # 08 Y:2006 | 08 | 2006 | ADJUST BURNERS FOR EFFICIENT OPERATION | $24,825 | $2,100 | Not Implemented |
IA0389 # 04 Y:2006 | 04 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,671 | $4,008 | Not Implemented |
IA0389 # 03 Y:2006 | 03 | 2006 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,332 | $322 | Not Implemented |
IA0389 # 02 Y:2006 | 02 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $376 | $42 | Not Implemented |
BD0313 # 04 Y:2006 | 04 | 2006 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $13,938 | $0 | Implemented |
BD0313 # 06 Y:2006 | 06 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,516 | $0 | Not Implemented |
BD0313 # 01 Y:2006 | 01 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $180,015 | $152 | Implemented |
BD0313 # 08 Y:2006 | 08 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,038 | $10,039 | Implemented |
BD0313 # 07 Y:2006 | 07 | 2006 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,780 | $800 | Implemented |
BD0313 # 03 Y:2006 | 03 | 2006 | MAKE ICE DURING OFF PEAK HOURS FOR COOLING | $162,249 | $310,000 | Not Implemented |
BD0313 # 02 Y:2006 | 02 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $12,962 | $5,000 | Implemented |
BD0313 # 09 Y:2006 | 09 | 2006 | INSTALL OCCUPANCY SENSORS | $3,815 | $1,275 | Implemented |
BD0313 # 05 Y:2006 | 05 | 2006 | INSTALL TURBULATORS | $2,094 | $1,500 | Implemented |
IA0388 # 08 Y:2006 | 08 | 2006 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $47,693 | $45,600 | Implemented |
IA0388 # 03 Y:2006 | 03 | 2006 | INSTALL OCCUPANCY SENSORS | $2,587 | $3,234 | Implemented |