IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

178

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
GT0724 # 01 Y:2001 01 2001 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,810 $8,370 n/a
GT0724 # 02 Y:2001 02 2001 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,554 $0 Not Implemented
GT0724 # 03 Y:2001 03 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,832 $1,800 Implemented
GT0724 # 04 Y:2001 04 2001 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $4,279 $5,900 Implemented
GT0724 # 05 Y:2001 05 2001 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $6,956 $7,500 Implemented
GT0724 # 06 Y:2001 06 2001 USE OPTIMUM TEMPERATURE $45,009 $3,850 Not Implemented
GT0723 # 02 Y:2001 02 2001 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $35,140 $68,913 Implemented
GT0723 # 03 Y:2001 03 2001 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $5,660 $825 Implemented
GT0723 # 04 Y:2001 04 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,036 $350 Implemented
GT0723 # 05 Y:2001 05 2001 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS $76,655 $0 Implemented
GT0723 # 06 Y:2001 06 2001 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $1,965 $1,418 Implemented
GT0723 # 01 Y:2001 01 2001 DE-ENERGIZE EXCESS TRANSFORMER CAPACITY $21,103 $60,000 Implemented
NC0226 # 04 Y:2001 04 2001 INSTALL / REPAIR INSULATION ON STEAM LINES $1,800 $400 Not Implemented
NC0226 # 03 Y:2001 03 2001 INSULATE BARE EQUIPMENT $2,071 $407 Not Implemented
NC0226 # 01 Y:2001 01 2001 DEVELOP A REPAIR/REPLACE POLICY $10,828 $12,834 Not Implemented
NC0226 # 07 Y:2001 07 2001 SUBSTITUTE COMPRESSED AIR COOLING WITH WATER OR AIR COOLING $23,668 $26,000 Not Implemented
NC0226 # 08 Y:2001 08 2001 REDUCE AIR CONDITIONING LOAD BY EVAPORATING WATER FROM ROOF $93,403 $-312,000 Not Implemented
NC0226 # 02 Y:2001 02 2001 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $3,348 $500 Not Implemented
NC0226 # 06 Y:2001 06 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $279 $150 Not Implemented
NC0226 # 05 Y:2001 05 2001 INSULATE BARE EQUIPMENT $1,122 $2,225 Not Implemented
NC0227 # 03 Y:2001 03 2001 INSTALL / REPAIR INSULATION ON STEAM LINES $662 $308 Not Implemented
NC0227 # 04 Y:2001 04 2001 IMPROVE COMBUSTION CONTROL CAPABILITY $89,586 $60,000 Not Implemented
NC0227 # 02 Y:2001 02 2001 TURN OFF EQUIPMENT WHEN NOT IN USE $15,815 $30,000 Not Implemented
NC0227 # 15 Y:2001 15 2001 $23,716 $15,000 Not Implemented
NC0227 # 05 Y:2001 05 2001 INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) $30,612 $50,000 Not Implemented