IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

229

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
NC0469 # 01 Y:2012 01 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $22,713 $129,851 Implemented
TT0099 # 03 Y:2012 03 2012 REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY $9,303 $10,800 Implemented
TT0099 # 02 Y:2012 02 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $17,777 $980 Implemented
NC0469 # 06 Y:2012 06 2012 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,526 $0 Implemented
NC0469 # 08 Y:2012 08 2012 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $288 $860 Implemented
NC0469 # 05 Y:2012 05 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $934 $200 Implemented
NC0472 # 05 Y:2012 05 2012 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $24 $0 Implemented
NC0472 # 02 Y:2012 02 2012 INSTALL OCCUPANCY SENSORS $845 $1,125 Not Implemented
NC0472 # 03 Y:2012 03 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $84 $200 Not Implemented
NC0472 # 04 Y:2012 04 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $188 $50 Implemented
NC0472 # 01 Y:2012 01 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,563 $16,950 Implemented
NC0470 # 09 Y:2012 09 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $9,234 $33,182 Not Implemented
NC0470 # 11 Y:2012 11 2012 UTILIZE OTHER METHODS TO REMOVE CONTAMINANTS $1,331,790 $2,000,000 Not Implemented
NC0470 # 01 Y:2012 01 2012 REDUCE EXCESSIVE BOILER BLOWDOWN $1,179 $0 Implemented
NC0470 # 03 Y:2012 03 2012 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,336 $1,200 Implemented
NC0470 # 04 Y:2012 04 2012 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $671 $1,100 Implemented
NC0470 # 07 Y:2012 07 2012 USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR $12,321 $36,400 Not Implemented
NC0470 # 05 Y:2012 05 2012 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $5,091 $400 Not Implemented
NC0470 # 08 Y:2012 08 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $39,181 $151,669 Implemented
NC0470 # 10 Y:2012 10 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $883 $1,575 Implemented
NC0470 # 06 Y:2012 06 2012 RECOVER WASTE HEAT FROM EQUIPMENT $35,967 $85,750 Not Implemented
NC0470 # 02 Y:2012 02 2012 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $11,916 $18,000 Not Implemented
NC0464 # 02 Y:2012 02 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,873 $35,445 Implemented
NC0464 # 04 Y:2012 04 2012 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $42,271 $58,000 Not Implemented
NC0464 # 03 Y:2012 03 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $79 $110 Implemented