IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

77

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK1021 # 01 Y:2019 01 2019 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS $957 $524 Implemented
OK1021 # 04 Y:2019 04 2019 INSTALL / REPAIR INSULATION ON STEAM LINES $6,865 $426 Implemented
OK1021 # 03 Y:2019 03 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,570 $850 Implemented
OK1021 # 05 Y:2019 05 2019 INSTALL SUB-METERING EQUIPMENT $5,665 $887 Not Implemented
OK1021 # 02 Y:2019 02 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,490 $4,312 Implemented
OK1017 # 01 Y:2019 01 2019 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $7,604 $17,500 Not Implemented
OK1017 # 03 Y:2019 03 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $22,220 $22,288 Not Implemented
OK1017 # 04 Y:2019 04 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,214 $3,590 Not Implemented
OK1017 # 05 Y:2019 05 2019 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $6,164 $0 Not Implemented
OK1017 # 02 Y:2019 02 2019 INSTALL / REPAIR INSULATION ON STEAM LINES $10,627 $231 Not Implemented
OK1016 # 03 Y:2019 03 2019 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $6,766 $9,480 Not Implemented
OK1016 # 07 Y:2019 07 2019 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC $485 $636 Implemented
OK1016 # 01 Y:2019 01 2019 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $27,210 $730 Not Implemented
OK1016 # 02 Y:2019 02 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,028 $28,358 Implemented
OK1016 # 06 Y:2019 06 2019 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT $885 $4,860 Not Implemented
OK1016 # 05 Y:2019 05 2019 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,523 $0 Not Implemented
OK1016 # 04 Y:2019 04 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,330 $0 Implemented
OK1015 # 05 Y:2019 05 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $427 $2,045 Implemented
OK1015 # 01 Y:2019 01 2019 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $16,383 $12,752 Not Implemented
OK1015 # 04 Y:2019 04 2019 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $380 $435 Not Implemented
OK1015 # 03 Y:2019 03 2019 INSTALL SET-BACK TIMERS $320 $200 Implemented
OK1015 # 02 Y:2019 02 2019 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $15,577 $17,500 Not Implemented
OK1011 # 06 Y:2019 06 2019 INSULATE BARE EQUIPMENT $5,110 $63 Not Implemented
OK1011 # 05 Y:2019 05 2019 OPTIMIZE PLANT POWER FACTOR $13,080 $57,161 Not Implemented
OK1011 # 04 Y:2019 04 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $43,176 $71,250 Implemented