Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

236

matching recommendations
Reset
SIC 243 Millwork, Plywood & Structural
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0519 # 05 Y:2007 05 2007 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $16,700 $35,900 Implemented
OR0519 # 02 Y:2007 02 2007 REDUCE EXCESS STEAM BLEEDING $548,400 $28,000 Implemented
OR0519 # 06 Y:2007 06 2007 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $102,000 $33,700 Implemented
OR0519 # 07 Y:2007 07 2007 UPGRADE CONTROLS ON COMPRESSORS $52,800 $40,500 Implemented
OR0519 # 08 Y:2007 08 2007 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $12,400 $12,400 Implemented
OR0519 # 09 Y:2007 09 2007 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $47,500 $109,300 Implemented
OR0516 # 02 Y:2007 02 2007 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $18,100 $37,100 Implemented
OR0516 # 03 Y:2007 03 2007 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $5,600 $15,300 Implemented
OR0516 # 04 Y:2007 04 2007 INSTALL OCCUPANCY SENSORS $5,300 $7,800 Implemented
OR0516 # 05 Y:2007 05 2007 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $3,400 $9,800 Implemented
OR0505 # 08 Y:2006 08 2006 CHANGE PRODUCT DESIGN TO REDUCE ENERGY REQUIREMENTS $168,270 $185,000 Implemented
OR0505 # 01 Y:2006 01 2006 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $18,900 $0 Implemented
OR0505 # 02 Y:2006 02 2006 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $4,600 $0 Implemented
OR0489 # 04 Y:2005 04 2005 USE PHOTOCELL CONTROLS $2,330 $100 Implemented
OR0489 # 02 Y:2005 02 2005 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $4,600 $340 Implemented
OR0489 # 10 Y:2005 10 2005 DIRECT WARMEST AIR TO COMBUSTION INTAKE $5,800 $12,000 Implemented
OR0489 # 07 Y:2005 07 2005 INSULATE BARE EQUIPMENT $1,800 $2,100 Implemented
OR0489 # 08 Y:2005 08 2005 INSTALL OCCUPANCY SENSORS $1,450 $3,590 Implemented
OR0489 # 05 Y:2005 05 2005 ADJUST VENTS TO MINIMIZE ENERGY USE $24,900 $12 Implemented
OR0468 # 02 Y:2004 02 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $9,200 $9,200 Implemented
OR0468 # 03 Y:2004 03 2004 REDESIGN FLOW TO MINIMIZE MASS TRANSFER LENGTH $3,000 $0 Implemented
OR0468 # 04 Y:2004 04 2004 UPGRADE CONTROLS ON COMPRESSORS $22,000 $1,200 Implemented
OR0468 # 07 Y:2004 07 2004 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $29,200 $27,800 Implemented
OR0468 # 09 Y:2004 09 2004 REDESIGN FLOW TO MINIMIZE MASS TRANSFER LENGTH $14,800 $15,700 Implemented
OR0468 # 10 Y:2004 10 2004 TURN OFF EQUIPMENT WHEN NOT IN USE $15,800 $26,600 Implemented