IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

44

matching recommendations
Reset
SIC 33 Primary Metal Industries
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
AM0225 # 08 Y:1994 08 1994 IMPROVED MATERIAL HANDLING (MIXING AND TRANSFER) $0 $7,500 Not Implemented
AM0225 # 09 Y:1994 09 1994 MODIFY MATERIAL APPLICATION METHODS $0 $7,500 Implemented
AM0225 # 07 Y:1994 07 1994 MINIMIZE CONTAMINATION OF WATER BEFORE TREATMENT $290 $0 Implemented
AM0225 # 03 Y:1994 03 1994 OPTIMIZE PLANT POWER FACTOR $10,500 $13,000 Not Implemented
AM0225 # 04 Y:1994 04 1994 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $2,260 $0 Implemented
AM0225 # 06 Y:1994 06 1994 USE A RAG RECYCLE SERVICE $1,440 $7,900 Implemented
AM0225 # 01 Y:1994 01 1994 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $33,100 $81,000 Implemented
AM0225 # 02 Y:1994 02 1994 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $13,670 $15,000 Implemented
AM0225 # 05 Y:1994 05 1994 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $730 $200 Implemented
AM0222 # 01 Y:1994 01 1994 COVER OPEN TANKS $10,970 $1,000 Implemented
AM0222 # 02 Y:1994 02 1994 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $4,300 $1,400 Implemented
AM0222 # 06 Y:1994 06 1994 PAY UTILITY BILLS ON TIME $722 $0 Implemented
AM0222 # 07 Y:1994 07 1994 INSULATE BARE EQUIPMENT $540 $150 Implemented
AM0222 # 03 Y:1994 03 1994 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,400 $740 Implemented
AM0222 # 04 Y:1994 04 1994 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $2,470 $0 Not Implemented
AM0222 # 05 Y:1994 05 1994 INSTALL SKYLIGHTS $1,580 $1,000 Implemented
AM0221 # 07 Y:1994 07 1994 RECYCLE CASTING SAND $63,410 $209,930 Not Implemented
AM0221 # 06 Y:1994 06 1994 USE LESS TOXIC AND VOLATILE SOLVENT SUBSTITUTES $1,040 $2,400 Not Implemented
AM0221 # 05 Y:1994 05 1994 RECYCLE CASTING SAND $37,570 $0 Implemented
AM0221 # 04 Y:1994 04 1994 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $3,180 $200 Implemented
AM0221 # 03 Y:1994 03 1994 REDUCE COMBUSTION AIR FLOW TO OPTIMUM $5,430 $0 Implemented
AM0221 # 02 Y:1994 02 1994 USE DEMAND CONTROLLER OR LOAD SHEDDER $9,930 $0 Not Implemented
AM0221 # 01 Y:1994 01 1994 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $58,720 $80,000 Not Implemented
AM0214 # 06 Y:1994 06 1994 INSULATE BARE EQUIPMENT $300 $0 Not Implemented
AM0214 # 05 Y:1994 05 1994 ADJUST BURNERS FOR EFFICIENT OPERATION $450 $680 Implemented