Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,582
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0260 # 04 Y:2024 | 04 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,557 | $6,277 | n/a |
UU0260 # 03 Y:2024 | 03 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,696 | $8,277 | n/a |
UU0260 # 02 Y:2024 | 02 | 2024 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $10,585 | $5,800 | n/a |
UU0260 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $27,825 | $247,680 | n/a |
UU0260 # 05 Y:2024 | 05 | 2024 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $726 | $3,000 | n/a |
UU0260 # 06 Y:2024 | 06 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $489 | $1,818 | n/a |
UU0261 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $22,296 | $572,100 | n/a |
UU0261 # 04 Y:2024 | 04 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,063 | $9,140 | n/a |
UU0261 # 03 Y:2024 | 03 | 2024 | CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE | $12,100 | $21,600 | n/a |
UU0261 # 05 Y:2024 | 05 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,386 | $8,280 | n/a |
UU0258 # 02 Y:2024 | 02 | 2024 | INSTALL / REPAIR INSULATION ON STEAM LINES | $25,800 | $6,200 | n/a |
UU0258 # 05 Y:2024 | 05 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,890 | $11,500 | n/a |
UU0258 # 03 Y:2024 | 03 | 2024 | IMPROVE COMBUSTION CONTROL CAPABILITY | $12,600 | $54,500 | n/a |
UU0258 # 06 Y:2024 | 06 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,570 | $5,140 | n/a |
UU0261 # 02 Y:2024 | 02 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $2,592 | $37,200 | n/a |
UU0258 # 01 Y:2024 | 01 | 2024 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $158,000 | $725,000 | n/a |
UU0261 # 06 Y:2024 | 06 | 2024 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $400 | $5,940 | n/a |
UU0258 # 08 Y:2024 | 08 | 2024 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $180,000 | $20,000 | n/a |
UU0258 # 04 Y:2024 | 04 | 2024 | USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | $1,690,000 | $23,500,000 | n/a |
UU0258 # 07 Y:2024 | 07 | 2024 | OPTIMIZE PLANT POWER FACTOR | $120,000 | $198,000 | n/a |
UU0259 # 02 Y:2024 | 02 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $221,450 | $2,473,450 | n/a |
UU0259 # 03 Y:2024 | 03 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $205,038 | $1,865,253 | n/a |
UU0259 # 04 Y:2024 | 04 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $68,165 | $110,030 | n/a |
UU0259 # 06 Y:2024 | 06 | 2024 | INSTALL COMMON HEADER ON COMPRESSORS | $3,995 | $9,200 | n/a |
UU0259 # 01 Y:2024 | 01 | 2024 | USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | $3,866,540 | $17,885,484 | n/a |