Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
35
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0343 # 04 Y:2006 | 04 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,918 | $0 | Implemented |
WV0343 # 02 Y:2006 | 02 | 2006 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $1,096,704 | $1,539,100 | Not Implemented |
WV0343 # 06 Y:2006 | 06 | 2006 | DEVELOP A REPAIR/REPLACE POLICY | $4,236 | $635 | Implemented |
WV0343 # 05 Y:2006 | 05 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $11,836 | $2,255 | Not Implemented |
WV0343 # 03 Y:2006 | 03 | 2006 | INSULATE BARE EQUIPMENT | $21,955 | $3,114 | Implemented |
WV0343 # 01 Y:2006 | 01 | 2006 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $1,166,408 | $1,460,000 | Not Implemented |
WV0341 # 11 Y:2006 | 11 | 2006 | DEVELOP A REPAIR/REPLACE POLICY | $501 | $213 | Implemented |
WV0341 # 02 Y:2006 | 02 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,073 | $1,800 | Implemented |
WV0341 # 01 Y:2006 | 01 | 2006 | USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR | $7,713 | $2,370 | Implemented |
WV0341 # 03 Y:2006 | 03 | 2006 | INSULATE BARE EQUIPMENT | $2,679 | $543 | Implemented |
WV0341 # 04 Y:2006 | 04 | 2006 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $2,635 | $2,695 | Not Implemented |
WV0341 # 05 Y:2006 | 05 | 2006 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,388 | $625 | Implemented |
WV0341 # 06 Y:2006 | 06 | 2006 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,532 | $600 | Not Implemented |
WV0341 # 07 Y:2006 | 07 | 2006 | INSTALL SPECTRAL REFLECTORS / DELAMP | $1,368 | $2,700 | Not Implemented |
WV0341 # 10 Y:2006 | 10 | 2006 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $571 | $525 | Not Implemented |
WV0341 # 12 Y:2006 | 12 | 2006 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $498 | $25 | Not Implemented |
WV0341 # 08 Y:2006 | 08 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,253 | $1,270 | Implemented |
WV0341 # 09 Y:2006 | 09 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $850 | $0 | Implemented |
WV0333 # 03 Y:2006 | 03 | 2006 | DEVELOP A REPAIR/REPLACE POLICY | $2,692 | $544 | Implemented |
WV0333 # 06 Y:2006 | 06 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $460 | $0 | Not Implemented |
WV0333 # 05 Y:2006 | 05 | 2006 | INSTALL OCCUPANCY SENSORS | $397 | $210 | Not Implemented |
WV0333 # 04 Y:2006 | 04 | 2006 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,819 | $800 | Implemented |
WV0333 # 02 Y:2006 | 02 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,663 | $195 | Implemented |
WV0333 # 01 Y:2006 | 01 | 2006 | BURN WASTE OIL FOR HEAT | $23,934 | $19,500 | Not Implemented |
WV0332 # 05 Y:2006 | 05 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,028 | $0 | Implemented |