IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,703

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
AS0513 # 05 Y:2022 05 2022 CONTRACT A WOOD PALLET RECYCLING COMPANY $11,700 $453 Not Implemented
AS0513 # 06 Y:2022 06 2022 ESTABLISH A PREVENTATIVE MAINTENANCE PROGRAM $6,454 $122 Not Implemented
AS0513 # 07 Y:2022 07 2022 INSTALL OCCUPANCY SENSORS $1,979 $1,772 Not Implemented
AS0513 # 08 Y:2022 08 2022 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,143 $411 Not Implemented
UU0194 # 01 Y:2022 01 2022 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $39,902 $83,130 Not Implemented
UU0194 # 02 Y:2022 02 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $37,721 $113,682 Implemented
UU0194 # 03 Y:2022 03 2022 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $25,369 $20,108 Not Implemented
UU0194 # 04 Y:2022 04 2022 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $5,610 $23,208 Implemented
UU0194 # 05 Y:2022 05 2022 INSTALL HEAT PIPES / RAISE COOLING SETPOINT $1,788 $2,208 Not Implemented
UU0194 # 06 Y:2022 06 2022 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $896 $1,796 Implemented
OR0749 # 01 Y:2022 01 2022 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $999 $0 Implemented
OR0749 # 02 Y:2022 02 2022 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT $43,522 $28,094 Not Implemented
OR0749 # 03 Y:2022 03 2022 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT $3,003 $11,329 Implemented
OR0749 # 04 Y:2022 04 2022 REPLACE BOILER $122,100 $1,640,000 Implemented
LS2203 # 01 Y:2022 01 2022 USE A DIFFERENT OR RECYCLED RAW MATERIAL $91,930 $8,070 Implemented
LS2203 # 02 Y:2022 02 2022 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $747 $300 Not Implemented
LS2203 # 03 Y:2022 03 2022 INSTALL OCCUPANCY SENSORS $179 $76 Implemented
LS2203 # 04 Y:2022 04 2022 MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS $40,432 $24,848 Not Implemented
LS2203 # 05 Y:2022 05 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,505 $3,841 Implemented
UF0570 # 01 Y:2022 01 2022 USE DEMAND CONTROLLER OR LOAD SHEDDER $61,494 $87,677 Implemented
UF0570 # 02 Y:2022 02 2022 INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS $15,702 $33,667 Implemented
UF0570 # 03 Y:2022 03 2022 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $12,945 $20,214 Implemented
UF0570 # 04 Y:2022 04 2022 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $12,034 $32,610 Implemented
UF0570 # 05 Y:2022 05 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $11,674 $35,369 Implemented
UF0570 # 06 Y:2022 06 2022 INSTALL OCCUPANCY SENSORS $4,026 $12,390 Not Implemented