Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
131
matching recommendationsNAICS | 311 | Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0780 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,517 | $2,000 | Implemented |
OR0773 # 02 Y:2023 | 02 | 2023 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,051 | $797 | Implemented |
OR0773 # 01 Y:2023 | 01 | 2023 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $5,439 | $1,278 | Implemented |
OR0768 # 03 Y:2023 | 03 | 2023 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $11,178 | $5,693 | Implemented |
OR0768 # 01 Y:2023 | 01 | 2023 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $18,535 | $8,125 | Implemented |
OR0749 # 04 Y:2022 | 04 | 2022 | REPLACE BOILER | $122,100 | $1,640,000 | Implemented |
OR0749 # 01 Y:2022 | 01 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $999 | $0 | Implemented |
OR0749 # 03 Y:2022 | 03 | 2022 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $3,003 | $11,329 | Implemented |
OR0744 # 05 Y:2021 | 05 | 2021 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $5,065 | $18,105 | Implemented |
OR0744 # 01 Y:2021 | 01 | 2021 | MINIMIZE WATER USAGE | $2,348 | $0 | Implemented |
OR0744 # 02 Y:2021 | 02 | 2021 | OPTIMIZE PLANT POWER FACTOR | $15,238 | $36,792 | Implemented |
OR0744 # 03 Y:2021 | 03 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $16,963 | $2,340 | Implemented |
OR0742 # 01 Y:2021 | 01 | 2021 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $4,010 | $0 | Implemented |
OR0742 # 02 Y:2021 | 02 | 2021 | REDESIGN PROCESS | $3,895 | $0 | Implemented |
OR0735 # 01 Y:2020 | 01 | 2020 | UPGRADE CONTROLS ON COMPRESSORS | $5,347 | $1,090 | Implemented |
OR0735 # 03 Y:2020 | 03 | 2020 | UPGRADE CONTROLS ON COMPRESSORS | $3,031 | $0 | Implemented |
OR0704 # 02 Y:2018 | 02 | 2018 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $127,144 | $201,450 | Implemented |
OR0656 # 01 Y:2015 | 01 | 2015 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $2,308,919 | $1,300,000 | Implemented |
OR0656 # 05 Y:2015 | 05 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,282 | $22,500 | Implemented |
OR0656 # 02 Y:2015 | 02 | 2015 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $188,688 | $247,000 | Implemented |
OR0656 # 03 Y:2015 | 03 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,591 | $27,789 | Implemented |
OR0647 # 01 Y:2015 | 01 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,826 | $4,986 | Implemented |
OR0647 # 04 Y:2015 | 04 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $24,576 | $25,575 | Implemented |
OR0641 # 01 Y:2014 | 01 | 2014 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $17,076 | $2,794 | Implemented |
OR0641 # 05 Y:2014 | 05 | 2014 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $581 | $1,121 | Implemented |