Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

128

matching recommendations
Reset
NAICS 311 Food Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0768 # 03 Y:2023 03 2023 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT $11,178 $5,693 Implemented
OR0768 # 01 Y:2023 01 2023 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $18,535 $8,125 Implemented
OR0749 # 04 Y:2022 04 2022 REPLACE BOILER $122,100 $1,640,000 Implemented
OR0749 # 01 Y:2022 01 2022 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $999 $0 Implemented
OR0749 # 03 Y:2022 03 2022 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT $3,003 $11,329 Implemented
OR0744 # 01 Y:2021 01 2021 MINIMIZE WATER USAGE $2,348 $0 Implemented
OR0744 # 03 Y:2021 03 2021 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $16,963 $2,340 Implemented
OR0744 # 02 Y:2021 02 2021 OPTIMIZE PLANT POWER FACTOR $15,238 $36,792 Implemented
OR0744 # 05 Y:2021 05 2021 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $5,065 $18,105 Implemented
OR0742 # 02 Y:2021 02 2021 REDESIGN PROCESS $3,895 $0 Implemented
OR0742 # 01 Y:2021 01 2021 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $4,010 $0 Implemented
OR0735 # 03 Y:2020 03 2020 UPGRADE CONTROLS ON COMPRESSORS $3,031 $0 Implemented
OR0735 # 01 Y:2020 01 2020 UPGRADE CONTROLS ON COMPRESSORS $5,347 $1,090 Implemented
OR0704 # 02 Y:2018 02 2018 UTILIZE A LESS EXPENSIVE COOLING METHOD $127,144 $201,450 Implemented
OR0656 # 05 Y:2015 05 2015 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $7,282 $22,500 Implemented
OR0656 # 01 Y:2015 01 2015 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $2,308,919 $1,300,000 Implemented
OR0656 # 02 Y:2015 02 2015 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY $188,688 $247,000 Implemented
OR0656 # 03 Y:2015 03 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $17,591 $27,789 Implemented
OR0647 # 04 Y:2015 04 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $24,576 $25,575 Implemented
OR0647 # 01 Y:2015 01 2015 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $5,826 $4,986 Implemented
OR0641 # 04 Y:2014 04 2014 INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS $1,470 $1,577 Implemented
OR0641 # 05 Y:2014 05 2014 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $581 $1,121 Implemented
OR0641 # 02 Y:2014 02 2014 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $13,580 $8,760 Implemented
OR0641 # 01 Y:2014 01 2014 REDUCE COMBUSTION AIR FLOW TO OPTIMUM $17,076 $2,794 Implemented
OR0632 # 04 Y:2014 04 2014 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $870 $500 Implemented