Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
689
matching recommendationsNAICS | 3114 | Fruit and Vegetable Preserving and Specialty Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0330 # 07 Y:2003 | 07 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,173 | $7,342 | Implemented |
IA0330 # 08 Y:2003 | 08 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $866 | $1,149 | Implemented |
IA0330 # 09 Y:2003 | 09 | 2003 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $2,303 | $0 | Implemented |
IA0330 # 10 Y:2003 | 10 | 2003 | INSTALL OCCUPANCY SENSORS | $684 | $1,064 | Implemented |
OR0440 # 01 Y:2003 | 01 | 2003 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $1,842,800 | $348,000 | Implemented |
OR0440 # 03 Y:2003 | 03 | 2003 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $16,500 | $5,130 | Implemented |
OR0440 # 05 Y:2003 | 05 | 2003 | ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS | $2,600 | $700 | Implemented |
OR0440 # 07 Y:2003 | 07 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $15,500 | $38,200 | Implemented |
OR0439 # 01 Y:2003 | 01 | 2003 | UTILIZE OTHER METHODS TO REMOVE CONTAMINANTS | $330,000 | $790,000 | Implemented |
OR0439 # 03 Y:2003 | 03 | 2003 | ADJUST BURNERS FOR EFFICIENT OPERATION | $10,500 | $450 | Implemented |
OR0439 # 04 Y:2003 | 04 | 2003 | INSTALL / REPAIR INSULATION ON STEAM LINES | $4,500 | $1,850 | Implemented |
OR0439 # 05 Y:2003 | 05 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,400 | $12,100 | Implemented |
OR0439 # 06 Y:2003 | 06 | 2003 | OPTIMIZE OPERATION OF MULTI-STAGE VACUUM STEAM JETS | $3,250 | $3,000 | Implemented |
WV0278 # 02 Y:2003 | 02 | 2003 | REPAIR AND ELIMINATE STEAM LEAKS | $27,508 | $204 | Implemented |
WV0278 # 03 Y:2003 | 03 | 2003 | REPAIR OR REPLACE STEAM TRAPS | $23,200 | $1,000 | Implemented |
WV0278 # 05 Y:2003 | 05 | 2003 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $18,480 | $504 | Implemented |
WV0278 # 08 Y:2003 | 08 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,418 | $42 | Implemented |
WV0278 # 09 Y:2003 | 09 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,387 | $7,590 | Implemented |
WV0278 # 10 Y:2003 | 10 | 2003 | INSULATE BARE EQUIPMENT | $3,709 | $258 | Implemented |
WV0278 # 11 Y:2003 | 11 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,990 | $0 | Implemented |
TA0050 # 02 Y:2003 | 02 | 2003 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $47,100 | $5,202 | Implemented |
TA0050 # 03 Y:2003 | 03 | 2003 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,258 | $8,100 | Implemented |
TA0050 # 05 Y:2003 | 05 | 2003 | UPGRADE OBSOLETE EQUIPMENT | $5,795 | $11,200 | Implemented |
TA0050 # 07 Y:2003 | 07 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,570 | $0 | Implemented |
TA0050 # 08 Y:2003 | 08 | 2003 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,676 | $0 | Implemented |