IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

31

matching recommendations
Reset
NAICS 321211 Hardwood Veneer and Plywood Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0728 # 04 Y:2019 04 2019 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $4,008 $0 Implemented
OR0638 # 07 Y:2014 07 2014 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $21,180 $10,000 Implemented
OR0638 # 04 Y:2014 04 2014 MINIMIZE WATER USAGE $1,003 $0 Implemented
OR0573 # 05 Y:2011 05 2011 INSTALL / REPAIR INSULATION ON STEAM LINES $11,543 $7,806 Implemented
OR0564 # 05 Y:2010 05 2010 USE OPTIMUM THICKNESS INSULATION $64,658 $105,222 Implemented
OR0564 # 02 Y:2010 02 2010 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $31,314 $31,314 Implemented
OR0555 # 04 Y:2010 04 2010 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $2,054 $1 Implemented
OR0555 # 03 Y:2010 03 2010 REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES $15,978 $11,900 Implemented
OR0548 # 08 Y:2009 08 2009 INSTALL / REPAIR INSULATION ON STEAM LINES $3,500 $600 Implemented
OR0548 # 07 Y:2009 07 2009 UPGRADE CONTROLS ON COMPRESSORS $7,349 $0 Implemented
OR0548 # 05 Y:2009 05 2009 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $9,882 $9,900 Implemented
OR0548 # 04 Y:2009 04 2009 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $15,295 $0 Implemented
OR0548 # 02 Y:2009 02 2009 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $47,605 $128,300 Implemented
OR0519 # 07 Y:2007 07 2007 UPGRADE CONTROLS ON COMPRESSORS $52,800 $40,500 Implemented
OR0519 # 09 Y:2007 09 2007 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $47,500 $109,300 Implemented
OR0519 # 08 Y:2007 08 2007 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $12,400 $12,400 Implemented
OR0519 # 06 Y:2007 06 2007 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $102,000 $33,700 Implemented
OR0519 # 05 Y:2007 05 2007 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $16,700 $35,900 Implemented
OR0519 # 02 Y:2007 02 2007 REDUCE EXCESS STEAM BLEEDING $548,400 $28,000 Implemented
OR0468 # 10 Y:2004 10 2004 TURN OFF EQUIPMENT WHEN NOT IN USE $15,800 $26,600 Implemented
OR0468 # 09 Y:2004 09 2004 REDESIGN FLOW TO MINIMIZE MASS TRANSFER LENGTH $14,800 $15,700 Implemented
OR0468 # 08 Y:2004 08 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $12,700 $13,800 Implemented
OR0468 # 07 Y:2004 07 2004 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $29,200 $27,800 Implemented
OR0468 # 04 Y:2004 04 2004 UPGRADE CONTROLS ON COMPRESSORS $22,000 $1,200 Implemented
OR0468 # 03 Y:2004 03 2004 REDESIGN FLOW TO MINIMIZE MASS TRANSFER LENGTH $3,000 $0 Implemented