Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

400

matching recommendations
Reset
NAICS 3251 Basic Chemical Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UU0258 # 05 Y:2024 05 2024 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $7,890 $11,500 Implemented
UU0258 # 07 Y:2024 07 2024 OPTIMIZE PLANT POWER FACTOR $120,000 $198,000 Implemented
UU0258 # 03 Y:2024 03 2024 IMPROVE COMBUSTION CONTROL CAPABILITY $12,600 $54,500 Implemented
UU0258 # 02 Y:2024 02 2024 INSTALL / REPAIR INSULATION ON STEAM LINES $25,800 $6,200 Implemented
IC0313 # 10 Y:2024 10 2024 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $3,979 $2,430 Implemented
IC0313 # 09 Y:2024 09 2024 REPAIR AND ELIMINATE STEAM LEAKS $19,590 $704 Implemented
IC0313 # 11 Y:2024 11 2024 INSULATE BARE EQUIPMENT $4,631 $8,869 Implemented
IC0313 # 02 Y:2024 02 2024 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,562 $0 Implemented
IC0313 # 01 Y:2024 01 2024 OPTIMIZE OPERATION OF MULTI-STAGE VACUUM STEAM JETS $9,651 $7,079 Implemented
IC0313 # 06 Y:2024 06 2024 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,557 $0 Implemented
MI0441 # 04 Y:2024 04 2024 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,377 $510 Implemented
MI0441 # 06 Y:2024 06 2024 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,124 $1,980 Implemented
MI0441 # 07 Y:2024 07 2024 INSTALL OCCUPANCY SENSORS $671 $1,203 Implemented
MI0441 # 03 Y:2024 03 2024 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $21,427 $1,306 Implemented
MI0441 # 01 Y:2024 01 2024 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $58,244 $186,000 Implemented
LS2406 # 01 Y:2024 01 2024 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,003 $50 Implemented
LS2406 # 03 Y:2024 03 2024 ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS $9,410 $28,500 Implemented
KS2321 # 01 Y:2023 01 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $89,035 $701,322 Implemented
KS2321 # 02 Y:2023 02 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,032 $5,480 Implemented
KS2321 # 03 Y:2023 03 2023 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $646 $1,328 Implemented
KS2321 # 06 Y:2023 06 2023 USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT $125,249 $627,000 Implemented
OK1093 # 03 Y:2023 03 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $29,830 $374,400 Implemented
OK1093 # 08 Y:2023 08 2023 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $12,354 $1,420 Implemented
OK1093 # 04 Y:2023 04 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,723 $1,260 Implemented
OK1093 # 11 Y:2023 11 2023 CHANGE METHOD OF DEIONIZED WATER PRODUCTION $98,980 $367,077 Implemented