Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
482
matching recommendationsNAICS | 3252 | Resin, Synthetic Rubber, and Artificial Synthetic Fibers and Filaments Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0535 # 08 Y:2016 | 08 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $691 | $30 | Implemented |
WV0535 # 09 Y:2016 | 09 | 2016 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $320 | $298 | Implemented |
WV0535 # 10 Y:2016 | 10 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $260 | $138 | Implemented |
SD0535 # 01 Y:2016 | 01 | 2016 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $324,317 | $112,783 | Implemented |
SD0535 # 03 Y:2016 | 03 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $25,449 | $42,926 | Implemented |
SD0535 # 05 Y:2016 | 05 | 2016 | INSTALL OCCUPANCY SENSORS | $7,184 | $6,400 | Implemented |
WM0088 # 06 Y:2016 | 06 | 2016 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $3,245 | $0 | Implemented |
AM0701 # 01 Y:2016 | 01 | 2016 | REPAIR OR REPLACE STEAM TRAPS | $515,000 | $75,000 | Implemented |
AM0701 # 02 Y:2016 | 02 | 2016 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $195,000 | $2,000 | Implemented |
AM0701 # 03 Y:2016 | 03 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $73,125 | $105,700 | Implemented |
AM0701 # 04 Y:2016 | 04 | 2016 | PAY UTILITY BILLS ON TIME | $57,500 | $0 | Implemented |
AM0701 # 06 Y:2016 | 06 | 2016 | USE SYNTHETIC LUBRICANT | $35,540 | $0 | Implemented |
AM0701 # 08 Y:2016 | 08 | 2016 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,420 | $210 | Implemented |
AM0701 # 09 Y:2016 | 09 | 2016 | INSULATE BARE EQUIPMENT | $1,325 | $1,200 | Implemented |
SF0479 # 02 Y:2016 | 02 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,025 | $210 | Implemented |
SF0479 # 03 Y:2016 | 03 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,397 | $4,166 | Implemented |
SF0479 # 04 Y:2016 | 04 | 2016 | INSTALL OCCUPANCY SENSORS | $846 | $2,490 | Implemented |
DL0159 # 01 Y:2016 | 01 | 2016 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $287,810 | $31,000 | Implemented |
DL0159 # 02 Y:2016 | 02 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $48,000 | $100,750 | Implemented |
DL0159 # 03 Y:2016 | 03 | 2016 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $7,300 | $17,825 | Implemented |
DL0159 # 04 Y:2016 | 04 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $28,590 | $188,100 | Implemented |
NC0559 # 01 Y:2016 | 01 | 2016 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $109,787 | $1,000 | Implemented |
NC0559 # 03 Y:2016 | 03 | 2016 | REPLACE HIGH RESISTANCE DUCTS, PIPES, AND FITTINGS | $4,003 | $1,000 | Implemented |
NC0559 # 06 Y:2016 | 06 | 2016 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $9,950 | $25,000 | Implemented |
NC0559 # 07 Y:2016 | 07 | 2016 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $34,146 | $10,000 | Implemented |