Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,572
matching recommendationsNAICS | 326 | Plastics and Rubber Products Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0501 # 02 Y:2013 | 02 | 2013 | UPGRADE CONTROLS ON COMPRESSORS | $35,397 | $25,000 | Implemented |
NC0501 # 03 Y:2013 | 03 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,920 | $100 | Implemented |
NC0501 # 04 Y:2013 | 04 | 2013 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $21,685 | $33,000 | Implemented |
NC0501 # 06 Y:2013 | 06 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $667 | $1,630 | Implemented |
NC0501 # 07 Y:2013 | 07 | 2013 | METER WASTE WATER | $3,326 | $4,200 | Implemented |
MI0250 # 01 Y:2013 | 01 | 2013 | TURN OFF EQUIPMENT WHEN NOT IN USE | $25,326 | $3,900 | Implemented |
MI0250 # 02 Y:2013 | 02 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,636 | $1,660 | Implemented |
MI0250 # 03 Y:2013 | 03 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,559 | $2,200 | Implemented |
MI0250 # 04 Y:2013 | 04 | 2013 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $4,256 | $80 | Implemented |
MI0250 # 05 Y:2013 | 05 | 2013 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,052 | $2,520 | Implemented |
MI0250 # 06 Y:2013 | 06 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,828 | $80 | Implemented |
MI0250 # 07 Y:2013 | 07 | 2013 | INSTALL SKYLIGHTS | $2,274 | $5,665 | Implemented |
CO0679 # 02 Y:2013 | 02 | 2013 | USE RADIANT HEATER FOR SPOT HEATING | $1,740 | $1,320 | Implemented |
CO0679 # 03 Y:2013 | 03 | 2013 | AIR CONDITION ONLY SPACE NECESSARY | $9,040 | $500 | Implemented |
CO0679 # 04 Y:2013 | 04 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,450 | $15,070 | Implemented |
UK1316 # 01 Y:2013 | 01 | 2013 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $21,600 | $0 | Implemented |
UK1316 # 03 Y:2013 | 03 | 2013 | OPTIMIZE PLANT POWER FACTOR | $9,386 | $1,600 | Implemented |
UK1316 # 06 Y:2013 | 06 | 2013 | INSULATE BARE EQUIPMENT | $2,534 | $3,475 | Implemented |
UK1316 # 08 Y:2013 | 08 | 2013 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $716 | $840 | Implemented |
WM0029 # 02 Y:2013 | 02 | 2013 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,542 | $1,240 | Implemented |
WM0029 # 05 Y:2013 | 05 | 2013 | TURN OFF EQUIPMENT WHEN NOT IN USE | $9,925 | $4,915 | Implemented |
WM0029 # 10 Y:2013 | 10 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,633 | $644 | Implemented |
SF0439 # 01 Y:2013 | 01 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,213 | $0 | Implemented |
SF0439 # 02 Y:2013 | 02 | 2013 | INSULATE BARE EQUIPMENT | $3,654 | $436 | Implemented |
SF0439 # 03 Y:2013 | 03 | 2013 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $34,286 | $4,843 | Implemented |