Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,003
matching recommendationsNAICS | 3261 | Plastics Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0185 # 07 Y:2021 | 07 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $491 | $255 | Implemented |
LS2103 # 01 Y:2021 | 01 | 2021 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $35,907 | $250 | Implemented |
LS2103 # 02 Y:2021 | 02 | 2021 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,807 | $428 | Implemented |
LS2103 # 03 Y:2021 | 03 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,440 | $900 | Implemented |
LS2103 # 04 Y:2021 | 04 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $31,154 | $39,829 | Implemented |
LS2103 # 05 Y:2021 | 05 | 2021 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $209,892 | $1,023,215 | Implemented |
DL0192 # 01 Y:2021 | 01 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,986 | $7,760 | Implemented |
DL0192 # 02 Y:2021 | 02 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $973 | $1,296 | Implemented |
DL0192 # 03 Y:2021 | 03 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,016 | $1,500 | Implemented |
DL0192 # 04 Y:2021 | 04 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,082 | $11,000 | Implemented |
DL0192 # 05 Y:2021 | 05 | 2021 | INSTALL TIMERS AND/OR THERMOSTATS | $2,042 | $175 | Implemented |
WV0606 # 03 Y:2021 | 03 | 2021 | DEVELOP A REPAIR/REPLACE POLICY | $7,177 | $729 | Implemented |
WV0606 # 04 Y:2021 | 04 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,685 | $50 | Implemented |
WV0606 # 05 Y:2021 | 05 | 2021 | INSULATE BARE EQUIPMENT | $2,253 | $314 | Implemented |
WV0606 # 06 Y:2021 | 06 | 2021 | INSTALL OCCUPANCY SENSORS | $1,819 | $595 | Implemented |
CL2104 # 05 Y:2021 | 05 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $22,742 | $2,100 | Implemented |
LE0504 # 01 Y:2021 | 01 | 2021 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $205 | $500 | Implemented |
LE0504 # 03 Y:2021 | 03 | 2021 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $3,847 | $12,000 | Implemented |
LE0504 # 04 Y:2021 | 04 | 2021 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $2,323 | $12,000 | Implemented |
LE0504 # 05 Y:2021 | 05 | 2021 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $61,283 | $360,000 | Implemented |
MZ0305 # 01 Y:2021 | 01 | 2021 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $1,825 | $9,000 | Implemented |
MZ0305 # 02 Y:2021 | 02 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $24,692 | $44,928 | Implemented |
MZ0305 # 03 Y:2021 | 03 | 2021 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $27,350 | $93,000 | Implemented |
MZ0305 # 04 Y:2021 | 04 | 2021 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $579 | $320 | Implemented |
MZ0305 # 05 Y:2021 | 05 | 2021 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $16,340 | $5,200 | Implemented |