92
matching recommendationsNAICS | 326112 | Plastics Packaging Film and Sheet (including Laminated) Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UL2306 # 02 Y:2023 | 02 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $336 | $600 | Implemented |
WM0195 # 08 Y:2023 | 08 | 2023 | INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS | $1,986 | $2,700 | Implemented |
WM0195 # 07 Y:2023 | 07 | 2023 | INSTALL OCCUPANCY SENSORS | $1,997 | $1,000 | Implemented |
WM0195 # 05 Y:2023 | 05 | 2023 | PAY BILLS ON TIME TO AVOID LATE FEES | $2,687 | $0 | Implemented |
WM0195 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,725 | $13,127 | Implemented |
WM0195 # 06 Y:2023 | 06 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,381 | $700 | Implemented |
UU0214 # 01 Y:2023 | 01 | 2023 | OPTIMIZE PLANT POWER FACTOR | $14,031 | $23,302 | Implemented |
UU0214 # 03 Y:2023 | 03 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,776 | $6,969 | Implemented |
UU0214 # 06 Y:2023 | 06 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $550 | $1,558 | Implemented |
UU0214 # 02 Y:2023 | 02 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $4,069 | $17,638 | Implemented |
UU0214 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,274 | $495 | Implemented |
UW2202 # 01 Y:2022 | 01 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $16,645 | $10,782 | Implemented |
UW2202 # 02 Y:2022 | 02 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,233 | $12,913 | Implemented |
UW2202 # 03 Y:2022 | 03 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,538 | $9,763 | Implemented |
UW2202 # 04 Y:2022 | 04 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $135,581 | $876,160 | Implemented |
LE0516 # 02 Y:2021 | 02 | 2021 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,124 | $1,200 | Implemented |
LE0516 # 01 Y:2021 | 01 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,511 | $200 | Implemented |
UU0172 # 01 Y:2021 | 01 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,439 | $15,243 | Implemented |
UU0172 # 05 Y:2021 | 05 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,814 | $7,952 | Implemented |
UU0172 # 08 Y:2021 | 08 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,268 | $212 | Implemented |
UU0172 # 09 Y:2021 | 09 | 2021 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,679 | $1,200 | Implemented |
UU0172 # 07 Y:2021 | 07 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,543 | $100 | Implemented |
UU0172 # 06 Y:2021 | 06 | 2021 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $3,039 | $17,334 | Implemented |
SD0590 # 02 Y:2019 | 02 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,948 | $0 | Implemented |
SD0590 # 04 Y:2019 | 04 | 2019 | INSTALL OCCUPANCY SENSORS | $319 | $585 | Implemented |