Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
222
matching recommendationsNAICS | 326299 | All Other Rubber Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0505 # 11 Y:2015 | 11 | 2015 | DEVELOP A REPAIR/REPLACE POLICY | $1,699 | $672 | Implemented |
WV0505 # 01 Y:2015 | 01 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,298 | $6,690 | Implemented |
WV0505 # 03 Y:2015 | 03 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,348 | $8,583 | Implemented |
WV0505 # 04 Y:2015 | 04 | 2015 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $7,847 | $1,000 | Implemented |
WV0505 # 05 Y:2015 | 05 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,847 | $345 | Implemented |
WV0505 # 07 Y:2015 | 07 | 2015 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,601 | $1,700 | Implemented |
WV0505 # 10 Y:2015 | 10 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,063 | $35 | Implemented |
WV0491 # 03 Y:2014 | 03 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,694 | $263 | Implemented |
WV0491 # 04 Y:2014 | 04 | 2014 | TURN OFF EQUIPMENT WHEN NOT IN USE | $4,434 | $500 | Implemented |
WV0491 # 05 Y:2014 | 05 | 2014 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,124 | $2,208 | Implemented |
WV0491 # 06 Y:2014 | 06 | 2014 | DEVELOP A REPAIR/REPLACE POLICY | $1,234 | $593 | Implemented |
WV0491 # 08 Y:2014 | 08 | 2014 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $541 | $235 | Implemented |
WV0491 # 02 Y:2014 | 02 | 2014 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $6,341 | $1,000 | Implemented |
WV0491 # 10 Y:2014 | 10 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $445 | $25 | Implemented |
SD0456 # 06 Y:2012 | 06 | 2012 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $3,322 | $7,503 | Implemented |
SD0456 # 10 Y:2012 | 10 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,050 | $200 | Implemented |
SD0456 # 08 Y:2012 | 08 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,790 | $600 | Implemented |
SD0456 # 07 Y:2012 | 07 | 2012 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,827 | $200 | Implemented |
SD0456 # 05 Y:2012 | 05 | 2012 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $4,297 | $500 | Implemented |
SD0456 # 03 Y:2012 | 03 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,264 | $10,398 | Implemented |
SD0456 # 02 Y:2012 | 02 | 2012 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $8,534 | $2,700 | Implemented |
WV0455 # 03 Y:2012 | 03 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,439 | $5,745 | Implemented |
WV0455 # 04 Y:2012 | 04 | 2012 | INSULATE BARE EQUIPMENT | $6,023 | $2,440 | Implemented |
WV0455 # 06 Y:2012 | 06 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,600 | $3,294 | Implemented |
WV0455 # 09 Y:2012 | 09 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,863 | $1,706 | Implemented |