Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
47
matching recommendationsNAICS | 327 | Nonmetallic Mineral Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UW2317 # 04 Y:2023 | 04 | 2023 | CHANGE PRODUCT DESIGN TO REDUCE ENERGY REQUIREMENTS | $31,756 | $1,000,000 | Implemented |
UW2317 # 05 Y:2023 | 05 | 2023 | IMPROVE COMBUSTION CONTROL CAPABILITY | $30,104 | $300,000 | Implemented |
UW2317 # 03 Y:2023 | 03 | 2023 | INSTALL STORM WINDOWS AND DOORS | $156 | $1,901 | Implemented |
UW2317 # 02 Y:2023 | 02 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $658 | $1,096 | Implemented |
UW2317 # 01 Y:2023 | 01 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $533 | $0 | Implemented |
UW2315 # 02 Y:2023 | 02 | 2023 | IMPROVE COMBUSTION CONTROL CAPABILITY | $30,104 | $300,000 | Implemented |
UW2315 # 01 Y:2023 | 01 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $6,189 | $1,896 | Implemented |
UW2308 # 03 Y:2023 | 03 | 2023 | INSTALL STORM WINDOWS AND DOORS | $145 | $1,901 | Implemented |
UW2308 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $206 | $1,815 | Implemented |
UW2308 # 05 Y:2023 | 05 | 2023 | IMPROVE COMBUSTION CONTROL CAPABILITY | $47,887 | $200,000 | Implemented |
UW2308 # 02 Y:2023 | 02 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $491 | $1,096 | Implemented |
UW2308 # 01 Y:2023 | 01 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,223 | $0 | Implemented |
UW2308 # 06 Y:2023 | 06 | 2023 | CHANGE PRODUCT DESIGN TO REDUCE ENERGY REQUIREMENTS | $36,635 | $0 | Implemented |
UW2305 # 04 Y:2023 | 04 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,031 | $0 | Implemented |
UW2305 # 03 Y:2023 | 03 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,115 | $5,102 | Implemented |
UW2305 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $704 | $4,074 | Implemented |
UW2305 # 02 Y:2023 | 02 | 2023 | REPLACE DC EQUIPMENT WITH AC EQUIPMENT | $3,266 | $4,565 | Implemented |
BS0061 # 03 Y:2015 | 03 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $223 | $702 | Implemented |
BS0061 # 01 Y:2015 | 01 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,605 | $74,360 | Implemented |
OR0597 # 04 Y:2012 | 04 | 2012 | INSTALL OCCUPANCY SENSORS | $3,853 | $3,853 | Implemented |
OR0597 # 01 Y:2012 | 01 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,480 | $9,480 | Implemented |
UW0042 # 03 Y:2010 | 03 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $24,225 | $81,585 | Implemented |
UW0028 # 04 Y:2009 | 04 | 2009 | INSTALL OCCUPANCY SENSORS | $12,524 | $1,960 | Implemented |
UW0028 # 06 Y:2009 | 06 | 2009 | METER WASTE WATER | $1,060 | $12,000 | Implemented |
UW0028 # 08 Y:2009 | 08 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $144 | $0 | Implemented |