Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
23
matching recommendationsNAICS | 327320 | Ready-Mix Concrete Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UW2317 # 05 Y:2023 | 05 | 2023 | IMPROVE COMBUSTION CONTROL CAPABILITY | $30,104 | $300,000 | Implemented |
UW2317 # 04 Y:2023 | 04 | 2023 | CHANGE PRODUCT DESIGN TO REDUCE ENERGY REQUIREMENTS | $31,756 | $1,000,000 | Implemented |
UW2317 # 03 Y:2023 | 03 | 2023 | INSTALL STORM WINDOWS AND DOORS | $156 | $1,901 | Implemented |
UW2317 # 02 Y:2023 | 02 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $658 | $1,096 | Implemented |
UW2317 # 01 Y:2023 | 01 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $533 | $0 | Implemented |
UW2315 # 02 Y:2023 | 02 | 2023 | IMPROVE COMBUSTION CONTROL CAPABILITY | $30,104 | $300,000 | Implemented |
UW2315 # 01 Y:2023 | 01 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $6,189 | $1,896 | Implemented |
UW2308 # 02 Y:2023 | 02 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $491 | $1,096 | Implemented |
UW2308 # 06 Y:2023 | 06 | 2023 | CHANGE PRODUCT DESIGN TO REDUCE ENERGY REQUIREMENTS | $36,635 | $0 | Implemented |
UW2308 # 05 Y:2023 | 05 | 2023 | IMPROVE COMBUSTION CONTROL CAPABILITY | $47,887 | $200,000 | Implemented |
UW2308 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $206 | $1,815 | Implemented |
UW2308 # 03 Y:2023 | 03 | 2023 | INSTALL STORM WINDOWS AND DOORS | $145 | $1,901 | Implemented |
UW2308 # 01 Y:2023 | 01 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,223 | $0 | Implemented |
UW2305 # 04 Y:2023 | 04 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,031 | $0 | Implemented |
UW2305 # 03 Y:2023 | 03 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,115 | $5,102 | Implemented |
UW2305 # 02 Y:2023 | 02 | 2023 | REPLACE DC EQUIPMENT WITH AC EQUIPMENT | $3,266 | $4,565 | Implemented |
UW2305 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $704 | $4,074 | Implemented |
BS0061 # 01 Y:2015 | 01 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,605 | $74,360 | Implemented |
BS0061 # 03 Y:2015 | 03 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $223 | $702 | Implemented |
OR0438 # 05 Y:2003 | 05 | 2003 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,500 | $150 | Implemented |
OR0438 # 03 Y:2003 | 03 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,000 | $3,000 | Implemented |
OR0438 # 02 Y:2003 | 02 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,950 | $0 | Implemented |
OR0438 # 01 Y:2003 | 01 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $9,850 | $24,500 | Implemented |