Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
268
matching recommendationsNAICS | 33122 | Rolling and Drawing of Purchased Steel |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0489 # 04 Y:2012 | 04 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,978 | $13,325 | Implemented |
IA0489 # 03 Y:2012 | 03 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,582 | $12,659 | Implemented |
IA0489 # 02 Y:2012 | 02 | 2012 | INSTALL OCCUPANCY SENSORS | $336 | $298 | Implemented |
SD0454 # 05 Y:2012 | 05 | 2012 | INSULATE BARE EQUIPMENT | $14,303 | $13,546 | Implemented |
SD0454 # 02 Y:2012 | 02 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,236 | $2,700 | Implemented |
SD0454 # 01 Y:2012 | 01 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,512 | $200 | Implemented |
LE0332 # 07 Y:2012 | 07 | 2012 | DEVELOP STANDARD OPERATING PROCEDURES | $6,689 | $0 | Implemented |
LE0332 # 08 Y:2012 | 08 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,829 | $40 | Implemented |
MA0676 # 04 Y:2011 | 04 | 2011 | INSULATE BARE EQUIPMENT | $1,721 | $2,750 | Implemented |
MA0676 # 01 Y:2011 | 01 | 2011 | OPTIMIZE PLANT POWER FACTOR | $204,367 | $98,845 | Implemented |
MA0676 # 05 Y:2011 | 05 | 2011 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $593 | $1,250 | Implemented |
OK0798 # 11 Y:2010 | 11 | 2010 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,120 | $1,991 | Implemented |
OK0798 # 08 Y:2010 | 08 | 2010 | INSULATE BARE EQUIPMENT | $8,199 | $2,430 | Implemented |
OK0798 # 07 Y:2010 | 07 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,000 | $0 | Implemented |
OK0798 # 06 Y:2010 | 06 | 2010 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $16,240 | $0 | Implemented |
OK0798 # 03 Y:2010 | 03 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,085 | $5,205 | Implemented |
OK0798 # 04 Y:2010 | 04 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $203 | $2,009 | Implemented |
OK0798 # 05 Y:2010 | 05 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $28,826 | $900 | Implemented |
UD0817 # 09 Y:2010 | 09 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,120 | $0 | Implemented |
UD0817 # 12 Y:2010 | 12 | 2010 | COVER OPEN TANKS | $10,386 | $0 | Implemented |
UD0817 # 01 Y:2010 | 01 | 2010 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $66,672 | $600 | Implemented |
UD0817 # 13 Y:2010 | 13 | 2010 | INSULATE BARE EQUIPMENT | $21,893 | $0 | Implemented |
UD0817 # 15 Y:2010 | 15 | 2010 | INSULATE BARE EQUIPMENT | $3,996 | $0 | Implemented |
UD0817 # 07 Y:2010 | 07 | 2010 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $628 | $0 | Implemented |
UD0817 # 11 Y:2010 | 11 | 2010 | USE OPTIMUM TEMPERATURE | $8,137 | $0 | Implemented |