Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
310
matching recommendationsNAICS | 3313 | Alumina and Aluminum Production and Processing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0692 # 04 Y:2015 | 04 | 2015 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $2,124 | $0 | Implemented |
AM0692 # 03 Y:2015 | 03 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,880 | $16,750 | Implemented |
AM0692 # 02 Y:2015 | 02 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,830 | $5,000 | Implemented |
AM0692 # 01 Y:2015 | 01 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $12,970 | $10,000 | Implemented |
UK1508 # 13 Y:2015 | 13 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $21,138 | $12,000 | Implemented |
UK1508 # 12 Y:2015 | 12 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,063 | $3,260 | Implemented |
UK1508 # 11 Y:2015 | 11 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $14,700 | $1,700 | Implemented |
UK1508 # 10 Y:2015 | 10 | 2015 | INSTALL COMMON HEADER ON COMPRESSORS | $4,650 | $2,950 | Implemented |
UK1508 # 08 Y:2015 | 08 | 2015 | UPGRADE OBSOLETE EQUIPMENT | $1,302 | $746 | Implemented |
UK1508 # 07 Y:2015 | 07 | 2015 | INSTALL OCCUPANCY SENSORS | $1,722 | $193 | Implemented |
MZ0187 # 05 Y:2015 | 05 | 2015 | REPAIR AND ELIMINATE STEAM LEAKS | $3,321 | $1,440 | Implemented |
MZ0187 # 02 Y:2015 | 02 | 2015 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $9,635 | $6,500 | Implemented |
MZ0187 # 03 Y:2015 | 03 | 2015 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $684 | $380 | Implemented |
MZ0187 # 04 Y:2015 | 04 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,096 | $5,600 | Implemented |
WV0506 # 02 Y:2015 | 02 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,853 | $7,076 | Implemented |
WV0506 # 05 Y:2015 | 05 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,457 | $7,450 | Implemented |
WV0506 # 07 Y:2015 | 07 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,579 | $270 | Implemented |
WV0506 # 10 Y:2015 | 10 | 2015 | DEVELOP A REPAIR/REPLACE POLICY | $790 | $1,205 | Implemented |
WV0506 # 09 Y:2015 | 09 | 2015 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $1,221 | $1,000 | Implemented |
WV0504 # 10 Y:2015 | 10 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $293 | $69 | Implemented |
WV0504 # 08 Y:2015 | 08 | 2015 | DEVELOP A REPAIR/REPLACE POLICY | $1,537 | $556 | Implemented |
WV0504 # 06 Y:2015 | 06 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,334 | $486 | Implemented |
WV0504 # 05 Y:2015 | 05 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,624 | $12 | Implemented |
WV0504 # 04 Y:2015 | 04 | 2015 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,984 | $500 | Implemented |
WV0504 # 02 Y:2015 | 02 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,645 | $15,271 | Implemented |