IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

594

matching recommendations
Reset
NAICS 3314 Nonferrous Metal (except Aluminum) Production and Processing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0644 # 03 Y:2015 03 2015 ELIMINATE/REDUCE AN OPERATION $106,634 $72,750 Implemented
OR0644 # 04 Y:2015 04 2015 UPGRADE CONTROLS ON COMPRESSORS $37,274 $20,400 Implemented
OR0644 # 05 Y:2015 05 2015 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $3,431 $1,600 Not Implemented
OR0644 # 06 Y:2015 06 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,865 $3,865 Implemented
SF0460 # 01 Y:2015 01 2015 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $14,832 $0 Not Implemented
SF0460 # 02 Y:2015 02 2015 REPAIR AND ELIMINATE STEAM LEAKS $5,167 $624 Implemented
SF0460 # 03 Y:2015 03 2015 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $10,080 $4,429 Not Implemented
SF0460 # 04 Y:2015 04 2015 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $2,945 $2,541 Not Implemented
SF0460 # 05 Y:2015 05 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,462 $9,228 Implemented
SF0460 # 06 Y:2015 06 2015 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $4,269 $9,057 Not Implemented
SF0460 # 07 Y:2015 07 2015 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $3,924 $9,629 Not Implemented
SF0460 # 08 Y:2015 08 2015 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,062 $3,703 Implemented
SU0377 # 01 Y:2015 01 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $854 $514 Implemented
SU0377 # 02 Y:2015 02 2015 RECOVER AND REUSE WASTE MATERIAL $1,281,641 $1,000,000 Not Implemented
SU0377 # 03 Y:2015 03 2015 ELIMINATE/REDUCE AN OPERATION $4,112 $3,576 Implemented
SU0377 # 04 Y:2015 04 2015 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,129 $998 Not Implemented
SU0377 # 05 Y:2015 05 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,883 $2,400 Implemented
SU0377 # 06 Y:2015 06 2015 OPTIMIZE PLANT POWER FACTOR $5,745 $12,259 Not Implemented
SU0377 # 07 Y:2015 07 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,638 $5,256 Implemented
UM0435 # 01 Y:2013 01 2013 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $4,450 $4,500 Implemented
UM0435 # 02 Y:2013 02 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,500 $200 Not Implemented
UM0435 # 03 Y:2013 03 2013 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $966 $2,500 Implemented
UM0435 # 04 Y:2013 04 2013 RECOVER WASTE HEAT FROM EQUIPMENT $2,000 $3,000 Implemented
MZ0121 # 01 Y:2013 01 2013 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $16,992 $0 Not Implemented
MZ0121 # 02 Y:2013 02 2013 RECOVER WASTE HEAT FROM EQUIPMENT $16,550 $1,370 Not Implemented