Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
447
matching recommendationsNAICS | 33232 | Ornamental and Architectural Metal Products Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0574 # 01 Y:2024 | 01 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $11,872 | $2,400 | Implemented |
LE0574 # 05 Y:2024 | 05 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $14,969 | $45,000 | Implemented |
LE0574 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $20,430 | $5,760 | Implemented |
LE0574 # 03 Y:2024 | 03 | 2024 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $32,332 | $69,375 | Implemented |
SU0545 # 07 Y:2023 | 07 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $669 | $83 | Implemented |
SD0646 # 01 Y:2024 | 01 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $678 | $180 | Implemented |
SD0646 # 05 Y:2024 | 05 | 2024 | USE BATTERY STORAGE FOR DEMAND CONTROL | $8,600 | $0 | Implemented |
SD0646 # 03 Y:2024 | 03 | 2024 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $503 | $614 | Implemented |
SD0646 # 12 Y:2024 | 12 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $9,254 | $250 | Implemented |
SD0646 # 04 Y:2024 | 04 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $81,600 | $250,043 | Implemented |
SD0646 # 11 Y:2024 | 11 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $516 | $250 | Implemented |
SD0646 # 02 Y:2024 | 02 | 2024 | ADJUST BURNERS FOR EFFICIENT OPERATION | $16,626 | $6,076 | Implemented |
SD0646 # 09 Y:2024 | 09 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $276 | $932 | Implemented |
SD0646 # 08 Y:2024 | 08 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,221 | $10,759 | Implemented |
SD0646 # 10 Y:2024 | 10 | 2024 | INSTALL DIRECT ACTING UNITS IN PLACE OF COMPRESSED AIR PRESSURE SYSTEM IN SAFETY SYSTEM | $4,515 | $6,200 | Implemented |
SD0646 # 06 Y:2024 | 06 | 2024 | ADOPT IN-HOUSE MATERIAL GENERATION | $32,881 | $97,356 | Implemented |
MI0431 # 07 Y:2023 | 07 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $816 | $1,400 | Implemented |
MI0431 # 03 Y:2023 | 03 | 2023 | OPTIMIZE PLANT POWER FACTOR | $8,963 | $16,003 | Implemented |
MI0431 # 05 Y:2023 | 05 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,269 | $1,020 | Implemented |
MI0431 # 04 Y:2023 | 04 | 2023 | INSTALL OCCUPANCY SENSORS | $8,323 | $680 | Implemented |
MI0431 # 06 Y:2023 | 06 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $5,030 | $80 | Implemented |
MI0430 # 01 Y:2023 | 01 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $25,630 | $580 | Implemented |
MI0430 # 06 Y:2023 | 06 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,813 | $470 | Implemented |
MI0430 # 05 Y:2023 | 05 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $1,834 | $7,288 | Implemented |
MI0430 # 07 Y:2023 | 07 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,292 | $1,980 | Implemented |