Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
21
matching recommendationsNAICS | 333 | Machinery Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0651 # 11 Y:2023 | 11 | 2023 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $140 | $656 | Implemented |
WV0651 # 09 Y:2023 | 09 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $430 | $217 | Implemented |
WV0651 # 06 Y:2023 | 06 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $846 | $228 | Implemented |
WV0651 # 03 Y:2023 | 03 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,830 | $2,314 | Implemented |
WV0651 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,789 | $14,056 | Implemented |
WV0630 # 02 Y:2022 | 02 | 2022 | INSTALL OCCUPANCY SENSORS | $2,677 | $7,291 | Implemented |
WV0630 # 07 Y:2022 | 07 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $305 | $510 | Implemented |
WV0630 # 06 Y:2022 | 06 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $371 | $911 | Implemented |
WV0630 # 05 Y:2022 | 05 | 2022 | UPGRADE CONTROLS ON COMPRESSORS | $405 | $1,431 | Implemented |
WV0630 # 04 Y:2022 | 04 | 2022 | MINIMIZE WATER USAGE | $706 | $2,559 | Implemented |
WV0630 # 03 Y:2022 | 03 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,523 | $279 | Implemented |
WV0608 # 05 Y:2021 | 05 | 2021 | DEVELOP A REPAIR/REPLACE POLICY | $746 | $300 | Implemented |
WV0608 # 04 Y:2021 | 04 | 2021 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $952 | $0 | Implemented |
WV0608 # 03 Y:2021 | 03 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,836 | $1,100 | Implemented |
WV0414 # 02 Y:2010 | 02 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,304 | $42,420 | Implemented |
WV0414 # 14 Y:2010 | 14 | 2010 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $388 | $1,735 | Implemented |
WV0414 # 12 Y:2010 | 12 | 2010 | DEVELOP A REPAIR/REPLACE POLICY | $1,318 | $740 | Implemented |
WV0414 # 11 Y:2010 | 11 | 2010 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,335 | $1,070 | Implemented |
WV0414 # 10 Y:2010 | 10 | 2010 | RECOVER MECHANICAL ENERGY | $1,362 | $1,000 | Implemented |
WV0414 # 08 Y:2010 | 08 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,467 | $3,614 | Implemented |
WV0414 # 03 Y:2010 | 03 | 2010 | REDUCE FLUID FLOW RATES | $7,185 | $280 | Implemented |