Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
116
matching recommendationsNAICS | 333911 | Pump and Pumping Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SU0384 # 01 Y:2015 | 01 | 2015 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $11,706 | $0 | Implemented |
SU0384 # 02 Y:2015 | 02 | 2015 | PAY BILLS ON TIME TO AVOID LATE FEES | $1,732 | $0 | Implemented |
SU0384 # 07 Y:2015 | 07 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,109 | $3,650 | Implemented |
CO0687 # 03 Y:2014 | 03 | 2014 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $3,110 | $1,500 | Implemented |
CO0687 # 01 Y:2014 | 01 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,210 | $2,210 | Implemented |
AM0659 # 03 Y:2014 | 03 | 2014 | OPTIMIZE PLANT POWER FACTOR | $4,840 | $18,470 | Implemented |
AM0659 # 04 Y:2014 | 04 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,040 | $250 | Implemented |
AM0659 # 02 Y:2014 | 02 | 2014 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $16,935 | $3,000 | Implemented |
LE0355 # 07 Y:2013 | 07 | 2013 | INSTALL TIMERS AND/OR THERMOSTATS | $1,174 | $1,200 | Implemented |
LE0355 # 04 Y:2013 | 04 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,970 | $2,640 | Implemented |
LE0355 # 09 Y:2013 | 09 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,879 | $1,000 | Implemented |
OK0859 # 14 Y:2013 | 14 | 2013 | REDUCE HEAT GAIN BY WINDOW TINTING | $372 | $0 | Implemented |
OK0859 # 13 Y:2013 | 13 | 2013 | REDUCE HEAT GAIN BY WINDOW TINTING | $3,200 | $6,500 | Implemented |
OK0859 # 02 Y:2013 | 02 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,187 | $7,856 | Implemented |
OK0859 # 06 Y:2013 | 06 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,550 | $3,000 | Implemented |
OK0859 # 10 Y:2013 | 10 | 2013 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $17,170 | $30,000 | Implemented |
AM0642 # 10 Y:2013 | 10 | 2013 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $171 | $0 | Implemented |
AM0642 # 09 Y:2013 | 09 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $750 | $9 | Implemented |
AM0642 # 08 Y:2013 | 08 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $954 | $2,680 | Implemented |
AM0642 # 07 Y:2013 | 07 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,220 | $400 | Implemented |
AM0642 # 06 Y:2013 | 06 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,230 | $500 | Implemented |
AM0642 # 05 Y:2013 | 05 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,332 | $636 | Implemented |
AM0642 # 04 Y:2013 | 04 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,645 | $2,652 | Implemented |
AM0642 # 03 Y:2013 | 03 | 2013 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $4,950 | $560 | Implemented |
AM0642 # 01 Y:2013 | 01 | 2013 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $14,225 | $0 | Implemented |