Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
411
matching recommendationsNAICS | 3345 | Navigational, Measuring, Electromedical, and Control Instruments Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD1044 # 04 Y:2022 | 04 | 2022 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $318 | $0 | Implemented |
DL0206 # 01 Y:2022 | 01 | 2022 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $917 | $0 | Implemented |
DL0206 # 03 Y:2022 | 03 | 2022 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,292 | $0 | Implemented |
DL0206 # 05 Y:2022 | 05 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,447 | $8,852 | Implemented |
DL0206 # 04 Y:2022 | 04 | 2022 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $14,028 | $27,352 | Implemented |
OK1066 # 05 Y:2022 | 05 | 2022 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $7,555 | $0 | Implemented |
OK1066 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,177 | $23,400 | Implemented |
CW0119 # 01 Y:2021 | 01 | 2021 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $4,804 | $0 | Implemented |
CW0119 # 02 Y:2021 | 02 | 2021 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $3,402 | $1,640 | Implemented |
CW0119 # 05 Y:2021 | 05 | 2021 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $8,381 | $6,000 | Implemented |
CW0119 # 07 Y:2021 | 07 | 2021 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $5,837 | $1,000 | Implemented |
UA0246 # 04 Y:2021 | 04 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $855 | $1,067 | Implemented |
UA0246 # 01 Y:2021 | 01 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,600 | $9,695 | Implemented |
OR0746 # 02 Y:2022 | 02 | 2022 | ELIMINATE/REDUCE AN OPERATION | $2,177 | $49 | Implemented |
SD0619 # 01 Y:2021 | 01 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,059 | $4,547 | Implemented |
WV0604 # 10 Y:2021 | 10 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $733 | $35 | Implemented |
WV0604 # 09 Y:2021 | 09 | 2021 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,302 | $4,100 | Implemented |
WV0604 # 07 Y:2021 | 07 | 2021 | DEVELOP A REPAIR/REPLACE POLICY | $1,749 | $672 | Implemented |
WV0604 # 02 Y:2021 | 02 | 2021 | INSTALL OCCUPANCY SENSORS | $20,602 | $23,284 | Implemented |
WV0604 # 03 Y:2021 | 03 | 2021 | INSULATE BARE EQUIPMENT | $18,040 | $7,122 | Implemented |
WV0604 # 04 Y:2021 | 04 | 2021 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $4,330 | $1,500 | Implemented |
WV0604 # 05 Y:2021 | 05 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,431 | $403 | Implemented |
WV0604 # 06 Y:2021 | 06 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,500 | $1,792 | Implemented |
MI0379 # 01 Y:2020 | 01 | 2020 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $192,230 | $217,000 | Implemented |
CO0739 # 03 Y:2020 | 03 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $291 | $185 | Implemented |