Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
106
matching recommendationsNAICS | 335 | Electrical Equipment, Appliance, and Component Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0050 # 06 Y:2010 | 06 | 2010 | INSTALL OCCUPANCY SENSORS | $500 | $400 | Not Implemented |
TT0034 # 01 Y:2009 | 01 | 2009 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $20,000 | $47,500 | Not Implemented |
TT0034 # 02 Y:2009 | 02 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,800 | $2,500 | Not Implemented |
TT0034 # 03 Y:2009 | 03 | 2009 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $3,250 | $4,800 | Not Implemented |
TT0034 # 04 Y:2009 | 04 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,900 | $800 | Implemented |
TT0034 # 05 Y:2009 | 05 | 2009 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $13,300 | $20,000 | Not Implemented |
TT0034 # 06 Y:2009 | 06 | 2009 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,950 | $5,000 | Not Implemented |
TT0034 # 07 Y:2009 | 07 | 2009 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $4,000 | $0 | Implemented |
TT0034 # 08 Y:2009 | 08 | 2009 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $2,400 | $0 | Implemented |
TT0027 # 01 Y:2008 | 01 | 2008 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $1,297 | $250 | Implemented |
TT0027 # 02 Y:2008 | 02 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,204 | $862 | Not Implemented |
TT0027 # 03 Y:2008 | 03 | 2008 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,340 | $5,000 | Implemented |
TT0027 # 04 Y:2008 | 04 | 2008 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $25,272 | $22,000 | Not Implemented |
TT0027 # 05 Y:2008 | 05 | 2008 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $16,221 | $30,000 | Not Implemented |
TT0022 # 01 Y:2008 | 01 | 2008 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $10,000 | $2,500 | Not Implemented |
TT0022 # 02 Y:2008 | 02 | 2008 | INSTALL / REPAIR INSULATION ON STEAM LINES | $23,950 | $15,491 | Not Implemented |
TT0022 # 03 Y:2008 | 03 | 2008 | UPGRADE CONTROLS ON COMPRESSORS | $23,300 | $50,530 | Not Implemented |
TT0022 # 04 Y:2008 | 04 | 2008 | REPAIR OR REPLACE STEAM TRAPS | $7,750 | $4,800 | Not Implemented |
TT0022 # 05 Y:2008 | 05 | 2008 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $13,400 | $13,400 | Not Implemented |
TT0022 # 06 Y:2008 | 06 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $22,600 | $10,900 | Not Implemented |
TT0022 # 07 Y:2008 | 07 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $154,961 | $376,774 | Not Implemented |
TT0022 # 08 Y:2008 | 08 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,022 | $14,263 | Not Implemented |
TT0022 # 09 Y:2008 | 09 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,966 | $13,554 | Not Implemented |
TT0022 # 10 Y:2008 | 10 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,304 | $26,136 | Not Implemented |
TT0022 # 11 Y:2008 | 11 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $308 | $150 | Not Implemented |