Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,801
matching recommendationsNAICS | 336 | Transportation Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0134 # 09 Y:2007 | 09 | 2007 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $1,787 | $0 | Implemented |
IC0134 # 10 Y:2007 | 10 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $382 | $1,026 | Implemented |
IC0136 # 01 Y:2007 | 01 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,802 | $9,080 | Implemented |
IC0136 # 02 Y:2007 | 02 | 2007 | INSTALL OCCUPANCY SENSORS | $2,224 | $5,038 | Implemented |
IC0136 # 04 Y:2007 | 04 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,389 | $3,105 | Implemented |
UD0769 # 01 Y:2007 | 01 | 2007 | TURN OFF EQUIPMENT WHEN NOT IN USE | $126,798 | $0 | Implemented |
UD0769 # 02 Y:2007 | 02 | 2007 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $119,000 | $0 | Implemented |
UD0769 # 03 Y:2007 | 03 | 2007 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $63,509 | $110,000 | Implemented |
UD0769 # 04 Y:2007 | 04 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $61,170 | $110,000 | Implemented |
UD0769 # 05 Y:2007 | 05 | 2007 | USE RADIANT HEATER FOR SPOT HEATING | $44,667 | $28,125 | Implemented |
UD0769 # 06 Y:2007 | 06 | 2007 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $39,200 | $130,000 | Implemented |
UD0769 # 07 Y:2007 | 07 | 2007 | TURN OFF EQUIPMENT WHEN NOT IN USE | $25,268 | $0 | Implemented |
UD0769 # 08 Y:2007 | 08 | 2007 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $23,200 | $400 | Implemented |
UD0769 # 11 Y:2007 | 11 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,569 | $3,275 | Implemented |
UD0769 # 13 Y:2007 | 13 | 2007 | UPGRADE CONTROLS ON COMPRESSORS | $3,980 | $0 | Implemented |
UD0769 # 14 Y:2007 | 14 | 2007 | REDUCE VENTILATION AIR | $2,208 | $590 | Implemented |
UD0769 # 15 Y:2007 | 15 | 2007 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $1,800 | $500 | Implemented |
UD0769 # 16 Y:2007 | 16 | 2007 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,447 | $520 | Implemented |
UD0769 # 17 Y:2007 | 17 | 2007 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,242 | $0 | Implemented |
LL0286 # 02 Y:2007 | 02 | 2007 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,092 | $696 | Implemented |
LL0286 # 04 Y:2007 | 04 | 2007 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $1,927 | $90 | Implemented |
LL0286 # 05 Y:2007 | 05 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,588 | $920 | Implemented |
LL0286 # 06 Y:2007 | 06 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,534 | $30 | Implemented |
LL0286 # 08 Y:2007 | 08 | 2007 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $519 | $798 | Implemented |
CO0606 # 01 Y:2007 | 01 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,880 | $620 | Implemented |