Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,344
matching recommendationsNAICS | 3363 | Motor Vehicle Parts Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UM0289 # 04 Y:2005 | 04 | 2005 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $16,576 | $2,500 | Implemented |
UM0289 # 05 Y:2005 | 05 | 2005 | REPAIR AND ELIMINATE STEAM LEAKS | $9,600 | $1,400 | Implemented |
UM0288 # 01 Y:2005 | 01 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,386 | $10,000 | Implemented |
UM0288 # 02 Y:2005 | 02 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,865 | $150 | Implemented |
UM0288 # 03 Y:2005 | 03 | 2005 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $1,004 | $400 | Implemented |
UM0288 # 05 Y:2005 | 05 | 2005 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $656 | $0 | Implemented |
UM0288 # 06 Y:2005 | 06 | 2005 | REDUCE VENTILATION AIR | $616 | $150 | Implemented |
UM0288 # 07 Y:2005 | 07 | 2005 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $159 | $25 | Implemented |
UM0288 # 10 Y:2005 | 10 | 2005 | INSTALL OCCUPANCY SENSORS | $90 | $600 | Implemented |
UD0725 # 03 Y:2005 | 03 | 2005 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $6,863 | $28,350 | Implemented |
UD0725 # 04 Y:2005 | 04 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,772 | $18,444 | Implemented |
UD0725 # 05 Y:2005 | 05 | 2005 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,315 | $1,320 | Implemented |
UD0725 # 08 Y:2005 | 08 | 2005 | INSULATE BARE EQUIPMENT | $1,968 | $0 | Implemented |
UD0725 # 09 Y:2005 | 09 | 2005 | INSTALL OCCUPANCY SENSORS | $1,788 | $728 | Implemented |
UM0287 # 02 Y:2005 | 02 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $22,506 | $675 | Implemented |
UM0287 # 03 Y:2005 | 03 | 2005 | RECOVER WASTE HEAT FROM EQUIPMENT | $17,467 | $1,200 | Implemented |
UM0287 # 04 Y:2005 | 04 | 2005 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $9,493 | $8,770 | Implemented |
UM0287 # 05 Y:2005 | 05 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,726 | $13,103 | Implemented |
UM0287 # 07 Y:2005 | 07 | 2005 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $6,116 | $1,000 | Implemented |
UM0287 # 08 Y:2005 | 08 | 2005 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $4,334 | $1,250 | Implemented |
GT0810 # 04 Y:2005 | 04 | 2005 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $11,228 | $6,378 | Implemented |
UM0286 # 03 Y:2005 | 03 | 2005 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $3,775 | $1,900 | Implemented |
UM0286 # 04 Y:2005 | 04 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,376 | $450 | Implemented |
UM0286 # 06 Y:2005 | 06 | 2005 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,608 | $75 | Implemented |
UM0286 # 09 Y:2005 | 09 | 2005 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $100 | $45 | Implemented |