Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
56
matching recommendationsNAICS | 3364 | Aerospace Product and Parts Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0512 # 02 Y:2006 | 02 | 2006 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $32,700 | $20,600 | Not Implemented |
OR0512 # 03 Y:2006 | 03 | 2006 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $7,000 | $5,000 | Implemented |
OR0512 # 04 Y:2006 | 04 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,300 | $5,000 | Implemented |
OR0512 # 05 Y:2006 | 05 | 2006 | UPGRADE CONTROLS ON COMPRESSORS | $4,400 | $7,500 | Implemented |
OR0512 # 01 Y:2006 | 01 | 2006 | INSTALL OCCUPANCY SENSORS | $100,600 | $5,500 | Implemented |
TA0131 # 05 Y:2006 | 05 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,400 | $0 | Implemented |
TA0131 # 04 Y:2006 | 04 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,450 | $120 | Implemented |
TA0131 # 03 Y:2006 | 03 | 2006 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $4,180 | $630 | Not Implemented |
TA0131 # 02 Y:2006 | 02 | 2006 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $9,225 | $60 | Not Implemented |
TA0131 # 01 Y:2006 | 01 | 2006 | UPGRADE CONTROLS ON COMPRESSORS | $18,180 | $16 | Implemented |
UU0112 # 03 Y:2006 | 03 | 2006 | CLOSE OFF UNNEEDED STEAM LINES | $140,530 | $250,000 | Not Implemented |
UU0112 # 01 Y:2006 | 01 | 2006 | TURN OFF EQUIPMENT WHEN NOT IN USE | $0 | $0 | Not Implemented |
UU0112 # 02 Y:2006 | 02 | 2006 | REPAIR OR REPLACE STEAM TRAPS | $121,540 | $8,720 | Not Implemented |
UU0112 # 06 Y:2006 | 06 | 2006 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,030 | $0 | Not Implemented |
UU0112 # 05 Y:2006 | 05 | 2006 | TURN OFF STEAM / HOT WATER LINES LEADING TO SPACE HEATING UNITS | $65,810 | $442,960 | Not Implemented |
UU0112 # 04 Y:2006 | 04 | 2006 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $69,680 | $200,000 | Not Implemented |
UU0106 # 04 Y:2006 | 04 | 2006 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,120 | $4,000 | Not Implemented |
UU0106 # 06 Y:2006 | 06 | 2006 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $590 | $500 | Not Implemented |
UU0106 # 05 Y:2006 | 05 | 2006 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $23,010 | $7,390 | Not Implemented |
UU0106 # 02 Y:2006 | 02 | 2006 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $43,630 | $20,000 | Not Implemented |
UU0106 # 03 Y:2006 | 03 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,510 | $3,780 | Not Implemented |
UU0106 # 01 Y:2006 | 01 | 2006 | OPTIMIZE PLANT POWER FACTOR | $19,900 | $40,020 | Not Implemented |
MA0607 # 06 Y:2006 | 06 | 2006 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $10,577 | $1,870 | Not Implemented |
MA0607 # 07 Y:2006 | 07 | 2006 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $6,860 | $3,500 | Not Implemented |
MA0607 # 05 Y:2006 | 05 | 2006 | USE UTILITY CONTROLLED POWER MANAGEMENT | $12,223 | $14,000 | Not Implemented |