Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
753
matching recommendationsSIC | 22 | Textile Mill Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0603 # 06 Y:2017 | 06 | 2017 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $21,836 | $50 | Implemented |
NC0603 # 07 Y:2017 | 07 | 2017 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $64,413 | $100,000 | Not Implemented |
NC0603 # 08 Y:2017 | 08 | 2017 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $19,341 | $30,000 | Implemented |
NC0595 # 01 Y:2017 | 01 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $29,435 | $144,553 | Not Implemented |
NC0595 # 02 Y:2017 | 02 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $896 | $100 | Implemented |
NC0595 # 03 Y:2017 | 03 | 2017 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $375 | $552 | Implemented |
NC0595 # 04 Y:2017 | 04 | 2017 | ISOLATE STEAM LINES TO AVOID HEATING AIR CONDITIONED AREAS | $3,516 | $400 | Implemented |
NC0595 # 05 Y:2017 | 05 | 2017 | RECOVER WASTE HEAT FROM EQUIPMENT | $910 | $2,000 | Not Implemented |
NC0589 # 01 Y:2017 | 01 | 2017 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $38,378 | $62,575 | Not Implemented |
NC0589 # 02 Y:2017 | 02 | 2017 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,080 | $19,100 | Not Implemented |
NC0589 # 03 Y:2017 | 03 | 2017 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $4,455 | $10,000 | Not Implemented |
NC0589 # 04 Y:2017 | 04 | 2017 | IMPROVE SPACE COMFORT CONDITIONING | $28,966 | $135,750 | Not Implemented |
NC0589 # 05 Y:2017 | 05 | 2017 | DISTILL CONTAMINATED SOLVENTS FOR REUSE | $11,593 | $10,750 | Not Implemented |
NC0589 # 06 Y:2017 | 06 | 2017 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,876 | $840 | Implemented |
NC0589 # 07 Y:2017 | 07 | 2017 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,357 | $1,000 | Implemented |
NC0589 # 08 Y:2017 | 08 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $29,155 | $66,186 | Implemented |
NC0589 # 09 Y:2017 | 09 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $541 | $300 | Implemented |
NC0589 # 10 Y:2017 | 10 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,050 | $100 | Implemented |
NC0579 # 01 Y:2016 | 01 | 2016 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $52,901 | $500 | Implemented |
NC0579 # 02 Y:2016 | 02 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $46,532 | $113,706 | Implemented |
NC0579 # 03 Y:2016 | 03 | 2016 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $17,247 | $50,000 | Not Implemented |
NC0579 # 04 Y:2016 | 04 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,076 | $200 | Implemented |
NC0579 # 05 Y:2016 | 05 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,661 | $8,900 | Not Implemented |
NC0579 # 06 Y:2016 | 06 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,575 | $3,000 | Implemented |
NC0579 # 07 Y:2016 | 07 | 2016 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,983 | $4,000 | Not Implemented |