IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,196

matching recommendations
Reset
SIC 23 Apparel And Other Textile Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
NC0230 # 09 Y:2002 09 2002 LIMIT AND CONTROL SECONDARY COMBUSTION AIR IN FURNACE $4,254 $3,500 Implemented
GT0724 # 03 Y:2001 03 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,832 $1,800 Implemented
GT0724 # 04 Y:2001 04 2001 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $4,279 $5,900 Implemented
GT0724 # 05 Y:2001 05 2001 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $6,956 $7,500 Implemented
GT0723 # 01 Y:2001 01 2001 DE-ENERGIZE EXCESS TRANSFORMER CAPACITY $21,103 $60,000 Implemented
GT0723 # 02 Y:2001 02 2001 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $35,140 $68,913 Implemented
GT0723 # 03 Y:2001 03 2001 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $5,660 $825 Implemented
GT0723 # 04 Y:2001 04 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,036 $350 Implemented
GT0723 # 05 Y:2001 05 2001 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS $76,655 $0 Implemented
GT0723 # 06 Y:2001 06 2001 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $1,965 $1,418 Implemented
IC0017 # 01 Y:2001 01 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $10,046 $900 Implemented
IC0017 # 02 Y:2001 02 2001 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $992 $5,433 Implemented
IC0017 # 04 Y:2001 04 2001 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $495 $1,246 Implemented
IC0017 # 05 Y:2001 05 2001 INSTALL SET-BACK TIMERS $3,498 $1,020 Implemented
IC0017 # 06 Y:2001 06 2001 INSULATE BARE EQUIPMENT $2,264 $1,714 Implemented
IC0017 # 08 Y:2001 08 2001 MODIFY STARTUP/SHUTDOWN TIMES $14,500 $0 Implemented
IC0017 # 09 Y:2001 09 2001 AUTOMATE PAYROLL SYSTEM $5,500 $1,040 Implemented
MI0021 # 02 Y:2001 02 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,770 $312 Implemented
MI0021 # 05 Y:2001 05 2001 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $3,250 $4,200 Implemented
GT0714 # 01 Y:2001 01 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $630 $250 Implemented
GT0714 # 05 Y:2001 05 2001 ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS $98,120 $175,000 Implemented
MS0180 # 01 Y:2001 01 2001 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $1,502 $50 Implemented
MS0180 # 04 Y:2001 04 2001 INSULATE BARE EQUIPMENT $162 $83 Implemented
MS0180 # 05 Y:2001 05 2001 INSTALL / REPAIR INSULATION ON STEAM LINES $70 $88 Implemented
MS0180 # 07 Y:2001 07 2001 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $63 $48 Implemented