Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
127
matching recommendationsSIC | 24 | Lumber And Wood Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0538 # 03 Y:2019 | 03 | 2019 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $11,027 | $7,692 | Implemented |
UF0538 # 02 Y:2019 | 02 | 2019 | INSTALL SKYLIGHTS | $11,989 | $45,500 | Implemented |
UF0538 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $25,744 | $52,547 | Implemented |
OR0722 # 03 Y:2019 | 03 | 2019 | USE OPTIMUM TEMPERATURE | $6,191 | $0 | Not Implemented |
OR0722 # 01 Y:2019 | 01 | 2019 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $42,047 | $1,000 | Implemented |
OR0722 # 02 Y:2019 | 02 | 2019 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $17,875 | $0 | Implemented |
OR0722 # 04 Y:2019 | 04 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,107 | $0 | Implemented |
OR0722 # 06 Y:2019 | 06 | 2019 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $28,751 | $129,960 | Not Implemented |
OR0722 # 05 Y:2019 | 05 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,488 | $1,110 | Not Implemented |
OR0722 # 07 Y:2019 | 07 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,941 | $15,179 | Not Implemented |
NC0636 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,929 | $16,627 | Implemented |
NC0636 # 02 Y:2019 | 02 | 2019 | INSTALL OCCUPANCY SENSORS | $362 | $871 | Not Implemented |
NC0636 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $184 | $60 | Implemented |
NC0636 # 04 Y:2019 | 04 | 2019 | REPLACE ELECTRIC MOTORS WITH BACK PRESSURE STEAM TURBINES AND USE EXHAUST STEAM FOR PROCESS HEAT | $27,892 | $85,000 | Not Implemented |
IP0120 # 02 Y:2019 | 02 | 2019 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $835 | $0 | Implemented |
IP0120 # 04 Y:2019 | 04 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $223 | $22 | Implemented |
IP0120 # 07 Y:2019 | 07 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,019 | $4,963 | Implemented |
IP0120 # 09 Y:2019 | 09 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $691 | $3,215 | Implemented |
IP0120 # 06 Y:2019 | 06 | 2019 | OPTIMIZE PLANT POWER FACTOR | $9,284 | $11,128 | Not Implemented |
IP0120 # 05 Y:2019 | 05 | 2019 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $473 | $256 | Implemented |
IP0120 # 03 Y:2019 | 03 | 2019 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $348 | $0 | Not Implemented |
IP0120 # 01 Y:2019 | 01 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,145 | $4 | Implemented |
IP0120 # 08 Y:2019 | 08 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,278 | $7,549 | Not Implemented |
MA0807 # 06 Y:2019 | 06 | 2019 | INSTALL / REPAIR INSULATION ON STEAM LINES | $558 | $470 | Implemented |
MA0807 # 05 Y:2019 | 05 | 2019 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $1,241 | $5,413 | Implemented |