Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
964
matching recommendationsSIC | 2421 | Sawmills And Planing Mills, General |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OKO952 # 01 Y:2016 | 01 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $39,072 | $32,000 | Implemented |
OKO952 # 04 Y:2016 | 04 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,021 | $29,085 | Implemented |
OKO952 # 05 Y:2016 | 05 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,284 | $6,222 | Implemented |
OKO952 # 07 Y:2016 | 07 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,312 | $0 | Implemented |
BS0081 # 01 Y:2016 | 01 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,089 | $4,550 | Implemented |
BS0081 # 02 Y:2016 | 02 | 2016 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $10,309 | $150 | Implemented |
BS0081 # 05 Y:2016 | 05 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $462 | $15 | Implemented |
BS0081 # 06 Y:2016 | 06 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $401 | $550 | Implemented |
MA0757 # 01 Y:2016 | 01 | 2016 | INCREASE AMOUNT OF CONDENSATE RETURNED | $95,137 | $37,800 | Implemented |
MA0757 # 04 Y:2016 | 04 | 2016 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $3,924 | $500 | Implemented |
OR0667 # 03 Y:2016 | 03 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,538 | $0 | Implemented |
OR0667 # 04 Y:2016 | 04 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,475 | $35,460 | Implemented |
WV0517 # 09 Y:2016 | 09 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $847 | $60 | Implemented |
WV0517 # 07 Y:2016 | 07 | 2016 | INSTALL OCCUPANCY SENSORS | $1,069 | $260 | Implemented |
WV0517 # 06 Y:2016 | 06 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,573 | $450 | Implemented |
WV0517 # 04 Y:2016 | 04 | 2016 | DEVELOP A REPAIR/REPLACE POLICY | $5,859 | $1,478 | Implemented |
WV0517 # 03 Y:2016 | 03 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $14,320 | $0 | Implemented |
WV0517 # 02 Y:2016 | 02 | 2016 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $7,474 | $1,000 | Implemented |
OR0665 # 01 Y:2016 | 01 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $21,044 | $11,800 | Implemented |
OR0665 # 05 Y:2016 | 05 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,434 | $0 | Implemented |
OR0662 # 05 Y:2015 | 05 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,683 | $6,683 | Implemented |
BS0062 # 03 Y:2015 | 03 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $703 | $447 | Implemented |
BS0062 # 05 Y:2015 | 05 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $629 | $15 | Implemented |
WV0513 # 05 Y:2015 | 05 | 2015 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $18,366 | $1,000 | Implemented |
WV0513 # 02 Y:2015 | 02 | 2015 | INSULATE BARE EQUIPMENT | $45,398 | $21,389 | Implemented |