Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
41
matching recommendationsSIC | 2421 | Sawmills And Planing Mills, General |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0096 # 01 Y:2012 | 01 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $463 | $0 | Implemented |
TT0096 # 03 Y:2012 | 03 | 2012 | REPAIR AND ELIMINATE STEAM LEAKS | $26,105 | $10,000 | Implemented |
TT0096 # 04 Y:2012 | 04 | 2012 | UPGRADE CONTROLS ON COMPRESSORS | $1,892 | $1,000 | Implemented |
LL0339 # 03 Y:2010 | 03 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $152,895 | $42,400 | Implemented |
LL0339 # 02 Y:2010 | 02 | 2010 | INCREASE AMOUNT OF CONDENSATE RETURNED | $204,298 | $966,460 | Implemented |
LL0339 # 01 Y:2010 | 01 | 2010 | REPAIR AND ELIMINATE STEAM LEAKS | $271,505 | $2,920 | Implemented |
AR0089 # 05 Y:1996 | 05 | 1996 | MAINTAIN MACHINES TO REDUCE LEAKS | $3,650 | $300 | Implemented |
AR0089 # 03 Y:1996 | 03 | 1996 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $196 | $75 | Implemented |
AR0089 # 01 Y:1996 | 01 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,855 | $7,290 | Implemented |
AR0088 # 04 Y:1996 | 04 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,799 | $9,100 | Implemented |
AR0088 # 06 Y:1996 | 06 | 1996 | MAINTAIN MACHINES TO REDUCE LEAKS | $616 | $500 | Implemented |
AR0088 # 05 Y:1996 | 05 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,971 | $20 | Implemented |
AR0037 # 05 Y:1994 | 05 | 1994 | REPLACE ELECTRIC MOTORS WITH BACK PRESSURE STEAM TURBINES AND USE EXHAUST STEAM FOR PROCESS HEAT | $30,719 | $5,500 | Implemented |
AR0037 # 04 Y:1994 | 04 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,105 | $50 | Implemented |
AR0037 # 03 Y:1994 | 03 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,520 | $767 | Implemented |
AR0037 # 02 Y:1994 | 02 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,890 | $3,320 | Implemented |
AR0037 # 01 Y:1994 | 01 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $7,587 | $2,180 | Implemented |
AR0029 # 01 Y:1994 | 01 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,142 | $8,050 | Implemented |
AR0030 # 03 Y:1994 | 03 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $391 | $106 | Implemented |
AR0030 # 02 Y:1994 | 02 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $7,832 | $6,280 | Implemented |
AR0030 # 01 Y:1994 | 01 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,414 | $445 | Implemented |
AR0029 # 06 Y:1994 | 06 | 1994 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,099 | $459 | Implemented |
AR0029 # 04 Y:1994 | 04 | 1994 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,232 | $1,100 | Implemented |
AR0029 # 03 Y:1994 | 03 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,836 | $327 | Implemented |
AR0029 # 02 Y:1994 | 02 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $7,927 | $1,991 | Implemented |