IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,700

matching recommendations
Reset
SIC 25 Furniture And Fixtures
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WI0431 # 02 Y:2002 02 2002 INSTALL TIMERS AND/OR THERMOSTATS $1,742 $600 Implemented
WI0431 # 05 Y:2002 05 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $205 $0 Implemented
WI0431 # 07 Y:2002 07 2002 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $282 $640 Implemented
WI0431 # 08 Y:2002 08 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $254 $90 Implemented
SU0142 # 02 Y:2002 02 2002 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE $42,602 $19,900 Implemented
SU0142 # 04 Y:2002 04 2002 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $3,958 $230 Implemented
UD0654 # 04 Y:2002 04 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,212 $0 Implemented
UD0654 # 05 Y:2002 05 2002 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $415 $200 Implemented
CO0507 # 02 Y:2002 02 2002 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $10,120 $15,380 Implemented
CO0507 # 03 Y:2002 03 2002 USE DEMAND CONTROLLER OR LOAD SHEDDER $5,150 $7,000 Implemented
CO0507 # 04 Y:2002 04 2002 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $817 $1,358 Implemented
CO0507 # 05 Y:2002 05 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,700 $330 Implemented
LM0043 # 01 Y:2002 01 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,510 $1,365 Implemented
LM0043 # 03 Y:2002 03 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,002 $250 Implemented
MS0211 # 02 Y:2002 02 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,516 $577 Implemented
MS0211 # 04 Y:2002 04 2002 INSTALL TIMERS AND/OR THERMOSTATS $675 $472 Implemented
MS0211 # 05 Y:2002 05 2002 DISCONNECT BALLASTS $442 $255 Implemented
MS0210 # 01 Y:2002 01 2002 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $24,185 $100 Implemented
MS0210 # 03 Y:2002 03 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,968 $405 Implemented
MS0210 # 04 Y:2002 04 2002 DISCONNECT BALLASTS $461 $495 Implemented
GT0737 # 01 Y:2002 01 2002 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $2,238 $5,018 Implemented
GT0737 # 04 Y:2002 04 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $715 $2,240 Implemented
GT0737 # 06 Y:2002 06 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,105 $4,013 Implemented
UU0024 # 01 Y:2002 01 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,471 $30 Implemented
UU0024 # 03 Y:2002 03 2002 RECOVER WASTE HEAT FROM EQUIPMENT $2,165 $1,441 Implemented