Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,525
matching recommendationsSIC | 25 | Furniture And Fixtures |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0179 # 04 Y:1997 | 04 | 1997 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,599 | $1,019 | Implemented |
IA0179 # 05 Y:1997 | 05 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,405 | $525 | Not Implemented |
IA0179 # 06 Y:1997 | 06 | 1997 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $475 | $75 | Not Implemented |
IA0179 # 07 Y:1997 | 07 | 1997 | INSTALL OCCUPANCY SENSORS | $167 | $166 | Implemented |
MS0098 # 01 Y:1997 | 01 | 1997 | OPTIMIZE PLANT POWER FACTOR | $4,696 | $1,800 | Implemented |
MS0098 # 02 Y:1997 | 02 | 1997 | RECOVER WASTE HEAT FROM EQUIPMENT | $11,479 | $16,045 | Not Implemented |
MS0098 # 03 Y:1997 | 03 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,796 | $9,988 | Implemented |
MS0098 # 04 Y:1997 | 04 | 1997 | USE COOLING TOWER WATER INSTEAD OF REFRIGERATION | $14,937 | $4,826 | Implemented |
MS0098 # 05 Y:1997 | 05 | 1997 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $7,885 | $23,672 | Not Implemented |
MS0098 # 06 Y:1997 | 06 | 1997 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $28,149 | $2,288 | Not Implemented |
MS0098 # 07 Y:1997 | 07 | 1997 | BURN WASTE OIL FOR HEAT | $1,627 | $2,628 | Not Implemented |
MS0098 # 08 Y:1997 | 08 | 1997 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $107,600 | $6,500 | Implemented |
MS0098 # 09 Y:1997 | 09 | 1997 | DISTILL CONTAMINATED SOLVENTS FOR REUSE | $19,279 | $15,000 | Not Implemented |
MS0098 # 10 Y:1997 | 10 | 1997 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $88,514 | $0 | Not Implemented |
DS0100 # 01 Y:1997 | 01 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,501 | $7,978 | Implemented |
DS0100 # 02 Y:1997 | 02 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $961 | $1,250 | Implemented |
DS0100 # 03 Y:1997 | 03 | 1997 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $3,757 | $775 | Implemented |
DS0100 # 04 Y:1997 | 04 | 1997 | DISTILL CONTAMINATED SOLVENTS FOR REUSE | $1,927 | $6,000 | Not Implemented |
DS0100 # 05 Y:1997 | 05 | 1997 | FILTER AND REUSE HYDRAULIC OIL | $300 | $160 | Not Implemented |
DS0100 # 06 Y:1997 | 06 | 1997 | CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE | $505 | $1,089 | Not Implemented |
DS0100 # 07 Y:1997 | 07 | 1997 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $89,400 | $0 | Not Implemented |
DS0100 # 08 Y:1997 | 08 | 1997 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $441,528 | $545,000 | Not Implemented |
AS0211 # 01 Y:1997 | 01 | 1997 | INSTALL OCCUPANCY SENSORS | $1,173 | $1,725 | Not Implemented |
AS0211 # 02 Y:1997 | 02 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,090 | $7,878 | Not Implemented |
AS0211 # 03 Y:1997 | 03 | 1997 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $526 | $30 | Implemented |