Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
125
matching recommendationsSIC | 275 | Commercial Printing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UL0177 # 03 Y:1997 | 03 | 1997 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $255 | $20 | Not Implemented |
UL0177 # 04 Y:1997 | 04 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $135 | $87 | Not Implemented |
UL0177 # 05 Y:1997 | 05 | 1997 | INSTALL TIMERS AND/OR THERMOSTATS | $679 | $400 | Not Implemented |
UL0177 # 06 Y:1997 | 06 | 1997 | RECYCLE WASTE INK AND CLEANUP SOLVENT | $26,400 | $0 | Not Implemented |
UL0177 # 07 Y:1997 | 07 | 1997 | RECYCLE CLEANING SOLVENT AND REUSE | $4,260 | $9,226 | Not Implemented |
UL0177 # 08 Y:1997 | 08 | 1997 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $16,922 | $0 | Not Implemented |
UL0176 # 01 Y:1997 | 01 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $802 | $1,661 | Implemented |
UL0176 # 02 Y:1997 | 02 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $136 | $3,180 | Not Implemented |
UL0176 # 03 Y:1997 | 03 | 1997 | RECYCLE WASTE INK AND CLEANUP SOLVENT | $45,321 | $0 | Not Implemented |
UL0176 # 04 Y:1997 | 04 | 1997 | PURCHASE EQUIPMENT INSTEAD OF LEASING | $11,180 | $4,500 | Not Implemented |
UL0176 # 05 Y:1997 | 05 | 1997 | CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE | $9,373 | $400 | Not Implemented |
UL0176 # 06 Y:1997 | 06 | 1997 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS | $355,776 | $77,600 | Not Implemented |
UL0169 # 01 Y:1996 | 01 | 1996 | OPTIMIZE PLANT POWER FACTOR | $6,640 | $3,694 | Implemented |
UL0169 # 02 Y:1996 | 02 | 1996 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,562 | $20 | Not Implemented |
UL0169 # 03 Y:1996 | 03 | 1996 | INSTALL TIMERS AND/OR THERMOSTATS | $102 | $200 | Implemented |
UL0169 # 04 Y:1996 | 04 | 1996 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $2,300 | $0 | Not Implemented |
UL0169 # 05 Y:1996 | 05 | 1996 | CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE | $3,802 | $500 | Not Implemented |
UL0141 # 01 Y:1995 | 01 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,392 | $40 | n/a |
UL0141 # 02 Y:1995 | 02 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,652 | $4,124 | n/a |
UL0141 # 03 Y:1995 | 03 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,025 | $1,429 | n/a |
UL0141 # 04 Y:1995 | 04 | 1995 | OPTIMIZE PLANT POWER FACTOR | $40,228 | $19,553 | n/a |
UL0141 # 05 Y:1995 | 05 | 1995 | RECYCLE WASTE INK AND CLEANUP SOLVENT | $18,324 | $0 | n/a |
UL0141 # 06 Y:1995 | 06 | 1995 | RECYCLE WASTE INK AND CLEANUP SOLVENT | $38,145 | $0 | n/a |
UL0140 # 01 Y:1995 | 01 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,583 | $50 | Not Implemented |
UL0140 # 02 Y:1995 | 02 | 1995 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $191 | $20 | Implemented |