Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
338
matching recommendationsSIC | 2819 | Industrial Inorganic Chemicals, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0166 # 04 Y:2000 | 04 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $823 | $500 | Implemented |
BD0166 # 07 Y:2000 | 07 | 2000 | REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL | $33,228 | $35,000 | Implemented |
BD0166 # 09 Y:2000 | 09 | 2000 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $1,759 | $6,500 | Implemented |
BD0166 # 10 Y:2000 | 10 | 2000 | REPAIR AND ELIMINATE STEAM LEAKS | $997 | $600 | Implemented |
BD0155 # 02 Y:2000 | 02 | 2000 | INSTALL OCCUPANCY SENSORS | $7,453 | $2,325 | Implemented |
BD0155 # 04 Y:2000 | 04 | 2000 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,322 | $7,130 | Implemented |
BD0155 # 05 Y:2000 | 05 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,686 | $3,137 | Implemented |
BD0155 # 08 Y:2000 | 08 | 2000 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,113 | $495 | Implemented |
BD0155 # 11 Y:2000 | 11 | 2000 | PAY BILLS ON TIME TO AVOID LATE FEES | $29,751 | $0 | Implemented |
IA0220 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,950 | $0 | Implemented |
IA0220 # 02 Y:1999 | 02 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,697 | $500 | Implemented |
IA0220 # 04 Y:1999 | 04 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,597 | $232 | Implemented |
OK0569 # 02 Y:1999 | 02 | 1999 | USE DISTILLATION, EVAPORATION TO REMOVE CONTAMINANTS | $74,871 | $125,000 | Implemented |
OK0569 # 03 Y:1999 | 03 | 1999 | REPAIR AND ELIMINATE STEAM LEAKS | $32,085 | $3,300 | Implemented |
OK0569 # 04 Y:1999 | 04 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $19,442 | $26,944 | Implemented |
OK0569 # 06 Y:1999 | 06 | 1999 | INSTALL / REPAIR INSULATION ON STEAM LINES | $5,140 | $13,288 | Implemented |
OK0569 # 07 Y:1999 | 07 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,918 | $6,195 | Implemented |
OK0569 # 08 Y:1999 | 08 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,833 | $3,098 | Implemented |
SD0219 # 01 Y:1999 | 01 | 1999 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $20,370 | $68,000 | Implemented |
SD0219 # 03 Y:1999 | 03 | 1999 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $412 | $144 | Implemented |
SD0219 # 06 Y:1999 | 06 | 1999 | CONVERT TO AQUEOUS CLEANING | $11,000 | $0 | Implemented |
SD0219 # 07 Y:1999 | 07 | 1999 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $5,400 | $2,000 | Implemented |
SD0219 # 08 Y:1999 | 08 | 1999 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $11,118 | $2,000 | Implemented |
SD0219 # 09 Y:1999 | 09 | 1999 | AUTOMATE FINISHING PROCESS | $58,252 | $11,700 | Implemented |
SD0219 # 10 Y:1999 | 10 | 1999 | SCHEDULE DELIVERIES ACCORDING TO DEMAND | $7,020 | $0 | Implemented |