Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
514
matching recommendationsSIC | 2821 | Plastics Materials And Resins |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KS2316 # 08 Y:2023 | 08 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $12,336 | $29,920 | Implemented |
KS2316 # 09 Y:2023 | 09 | 2023 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $49,691 | $246,356 | Implemented |
KS2316 # 01 Y:2023 | 01 | 2023 | REPAIR AND ELIMINATE STEAM LEAKS | $11,534 | $2,766 | Implemented |
WV0643 # 09 Y:2023 | 09 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $418 | $100 | Implemented |
WV0643 # 01 Y:2023 | 01 | 2023 | INSTALL OCCUPANCY SENSORS | $4,345 | $8,691 | Implemented |
WV0643 # 04 Y:2023 | 04 | 2023 | INSULATE BARE EQUIPMENT | $1,534 | $2,013 | Implemented |
WV0643 # 03 Y:2023 | 03 | 2023 | INSTALL SET-BACK TIMERS | $3,513 | $1,125 | Implemented |
WV0643 # 10 Y:2023 | 10 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $73 | $215 | Implemented |
WV0643 # 08 Y:2023 | 08 | 2023 | UPGRADE CONTROLS ON COMPRESSORS | $603 | $1,520 | Implemented |
WV0643 # 05 Y:2023 | 05 | 2023 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $966 | $3,959 | Implemented |
WV0643 # 06 Y:2023 | 06 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $829 | $2,567 | Implemented |
WV0643 # 07 Y:2023 | 07 | 2023 | DEVELOP A REPAIR/REPLACE POLICY | $693 | $671 | Implemented |
DL0213 # 04 Y:2022 | 04 | 2022 | REPAIR OR REPLACE STEAM TRAPS | $92,874 | $102,000 | Implemented |
DL0213 # 01 Y:2022 | 01 | 2022 | ADJUST BURNERS FOR EFFICIENT OPERATION | $81,353 | $115,000 | Implemented |
MZ0332 # 08 Y:2022 | 08 | 2022 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $58,961 | $200,000 | Implemented |
MZ0332 # 01 Y:2022 | 01 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,571 | $18,580 | Implemented |
MZ0332 # 04 Y:2022 | 04 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,676 | $1,330 | Implemented |
LS2216 # 04 Y:2022 | 04 | 2022 | INSTALL OCCUPANCY SENSORS | $1,095 | $350 | Implemented |
LS2216 # 05 Y:2022 | 05 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $48,044 | $18,502 | Implemented |
LS2216 # 03 Y:2022 | 03 | 2022 | USE PHOTOCELL CONTROLS | $251 | $74 | Implemented |
GT0959 # 01 Y:2021 | 01 | 2021 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $11,495 | $800 | Implemented |
GT0959 # 03 Y:2021 | 03 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,641 | $1,850 | Implemented |
GT0959 # 04 Y:2021 | 04 | 2021 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $170 | $315 | Implemented |
GT0959 # 02 Y:2021 | 02 | 2021 | INSTALL TIMERS AND/OR THERMOSTATS | $184 | $50 | Implemented |
TT0268 # 05 Y:2022 | 05 | 2022 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $4,223 | $500 | Implemented |